Meeting Briefs

Will County Awards $10.4 Million Contract for Bell Road Widening in Homer Glen Area

Spread the love

Will County Public Works & Transportation Committee Meeting October 7, 2025

Article Summary: The Will County Public Works & Transportation Committee on Tuesday confirmed the award of a $10.4 million contract to P.T. Ferro Construction Co. for the major reconstruction and widening of a segment of Bell Road. The project, spanning from 151st Street to Martingale Lane, is expected to begin in November 2025 and will include new sidewalks, storm sewers, and modernized traffic signals.

Bell Road Project Key Points:

  • P.T. Ferro Construction Co. was the low bidder for the project with a bid of $10,400,058.22.

  • The project involves roadway widening and reconstruction on Bell Road (County Highway 16) from 151st Street to Martingale Lane.

  • Work is scheduled to begin in November 2025 and is estimated to be completed by November 20, 2026.

  • The roadway will remain open during construction with periodic lane closures controlled by flaggers.

JOLIET, IL – A significant road improvement project is set to begin in the Homer Glen area next year after the Will County Public Works & Transportation Committee on Tuesday, October 7, 2025, approved a $10.4 million construction contract.

The committee unanimously confirmed the award to Joliet-based P.T. Ferro Construction Co., which submitted the lowest bid for the reconstruction and widening of Bell Road (County Highway 16) between 151st Street and Martingale Lane. The contract is for $10,400,058.22.

The project is a major undertaking aimed at improving traffic flow and safety along the busy corridor. According to a project summary from the Will County Division of Transportation, the scope of work includes roadway widening and reconstruction with new pavement, installation of sidewalks and storm sewers, and modernization of traffic signals. The project will also involve building a soldier pile retaining wall, new street lighting, and pavement markings.

Construction is slated to begin in November 2025, with an estimated completion date of November 20, 2026. Officials have stated that Bell Road will remain open to traffic throughout the construction period, though drivers should expect periodic lane closures controlled by flaggers.

The contract was awarded following a bid letting on September 17, 2025.

The resolution confirming the contract award will now go to the full Will County Board for final approval at its October 16 meeting. Funding for the improvements will come from a combination of sources, including Motor Fuel Tax, RTA Tax, and County Highway Tax funds.

Events

No events

Leave a Comment





Latest News Stories

Meeting Briefs

Meeting Summary and Briefs: New Lenox School District 122 for August 2025

Meeting Summary and Briefs: New Lenox School District 122 Meeting | August 2025 The New Lenox School District 122 Board of Education took a major step toward modernizing another of...
WCO 2025-09-27 at 9.04.56 AM

Will County Reverses Zoning on Peotone Farmland to Facilitate 10-Acre Sale

Article Summary: The Will County Board unanimously approved a request to rezone a 10.08-acre portion of a property in Will Township back to agricultural use, reversing a 2023 zoning change....
Meeting Briefs

Meeting Summary and Briefs: Joliet Junior College Board of Trustees for September 10, 2025

Joliet Junior College Board of Trustees Meeting | September 2025 The Joliet Junior College (JJC) Board of Trustees approved a landmark agreement with the City of Joliet to explore a...
Screenshot

Lincoln-Way 210 Board Approves $172.7 Million Budget with Planned Deficit for Bus Purchases

Article Summary: The Lincoln-Way Community High School District 210 Board of Education approved the Fiscal Year 2026 budget, which includes a planned operating deficit of $814,000 to accommodate the purchase of...
Meeting Briefs

Meeting Summary and Briefs: New Lenox Community Park District for August 2025

New Lenox Community Park District Meeting | August 2025 The New Lenox Community Park District Board of Commissioners reviewed major financial news and celebrated a record-breaking month for its golf...
Pavlov Media

Pavlov Media to Bring New Fiber Internet Option to New Lenox

Village of New Lenox Board of Trustees Meeting | September 22, 2025 Article Summary: The entrance to the Wintrust Crossroads Sports Complex is set to receive a major aesthetic upgrade...
Enbridge Energy

Will County to Pay Enbridge $82,000 to Relocate Pipeline Equipment for Exchange Street Improvements

Article Summary: Will County will reimburse Enbridge Energy for costs associated with relocating its pipeline facilities to make way for roadway improvements on Exchange Street in the Monee and Crete...
diamond shaped orange red reflector street sign that reads road

Laraway Road Widening Project in New Lenox and Frankfort Gets Additional $468,000 for Redesign

Article Summary: The Will County Board approved a supplemental agreement worth $468,374 for additional design and engineering work on the major Laraway Road expansion project. The funds are needed for...
solar panels photovoltaics in solar farm

“Federal Policy Uncertainty” Blamed for Delay of Peotone Solar Farm; County Grants Second Extension

Article Summary: The Will County Board has granted a second permit extension for a solar farm in Peotone Township after the developer, Trajectory Energy Partners, cited "ongoing uncertainty regarding federal...
solar panels photovoltaics in solar farm

Will County Grants Extensions to Five Solar Projects Sold to New Developers

Article Summary: The Will County Board approved first-time permit extensions for five commercial solar projects across Monee, Crete, and Joliet townships, all of which were recently sold to larger energy...
WCO 2025-09-27 at 9.04.10 AM

Will County Board Approves Controversial Drug Recovery Retreat in Crete Township

Article Summary: The Will County Board has approved a special use permit for The Second Story Foundation to operate a long-term residential recovery program for men on a 68-acre horse...
new-lenox-fire-district-stations.3

Winter Start Unlikely for $4 Million New Lenox Fire Station 62 Remodel

New Lenox Fire Protection District Meeting | August 2025 Article Summary: The planned $4 million remodel of New Lenox Fire Station 62 faces a potential delay, as officials indicated a...
LWSRA-Blue-Logo-transparent

New LWSRA Sensory Bus Hits the Road Thanks to $30,000 Donation

New Lenox Community Park District Meeting | August 2025 Article Summary: The Lincoln-Way Special Recreation Association's new Sensory Bus is officially in service and has been well-received at community events....
Joliet-Junior-college.-Graphic-Logo.4

Joliet Junior College Honors Seven Long-Serving Employees Upon Retirement

Joliet Junior College Board of Trustees Meeting | September 2025 Article SummaryThe Joliet Junior College Board of Trustees formally recognized seven long-serving employees who are retiring, including Dr. Robert "Bob"...
New-Lenox-School-122.3

New Lenox Parent Challenges Busing Fee, Cites Safety Concerns and Budget Surplus

Meeting Summary and Briefs: New Lenox School District 122 Meeting | August 2025 Article Summary: A New Lenox parent addressed the School District 122 board to protest a $350 busing...