Renovations at Veterans Assistance Commission and Court Annex on Track for Winter Completion
Article Summary: Will County’s new Veterans Assistance Commission facility in Joliet is projected to be completed by December, while major renovations for the State’s Attorney’s office in the Court Annex are on schedule for a November move-in. Director of Facilities Bill Fern updated a county committee on the progress of these and other key capital projects across the county.
Capital Projects Update Key Points:
-
Interior renovations at the Veterans Assistance Commission buildout at 1300 Copperfield are underway, with a target completion of December 2025.
-
The Court Annex renovations for the State’s Attorney’s office at 57 N. Ottawa are nearing completion and on track for a November 2025 move-in.
-
A potential delay in the delivery of rooftop air handlers for the VAC building is being monitored by the facilities department.
-
Other completed projects include exterior stone repairs at the new courthouse and the installation of speed bumps at the county office building.
JOLIET, IL — Two major Will County building projects are nearing the finish line, with the new Veterans Assistance Commission (VAC) facility expected to open by December and the State’s Attorney’s office set to move into its renovated space in November.
Will County Director of Facilities Bill Fern provided the updates to the Capital Improvements & IT Committee on Tuesday, October 7, 2025.
The buildout of the former Copperfield building at 1300 Copperfield for the VAC is progressing well, with mechanical, lighting, and security systems currently being installed. Fern noted one potential issue that staff is monitoring closely. “The air handling units for the rooftop… the timeline for shipment has been delayed twice,” he said. “We’re coming into the critical point where we’re going to need to condition the space for heat, not air.” Despite the potential delay, the project is still aiming for completion by the end of the year.
Meanwhile, renovations on the second level of the Court Annex building at 57 N. Ottawa for the State’s Attorney’s office are moving quickly. “We’re in a finished space now with the carpet down,” Fern reported, adding that the project is on track for its November move-in date. The remodel includes opening up previously sealed windows to provide natural light to the new offices.
Fern also reported on several smaller projects, including the recent installation of speed bumps and fresh striping in the parking lot of the Will County Office Building to improve pedestrian safety. He also noted that exterior stone repairs on the new courthouse are complete, with scaffolding now removed, at no cost to the county.
Latest News Stories
Land Use Committee Advances Mokena Scrap Yard and Homer Glen Landscape Business Over Local Objections
District 210 Reports Insurance Deficit Amid National Healthcare Cost Spikes; Finances Remain Stable
Foxx to face questions about murder conviction review ‘investigations’
Illinois Quick Hits: North Chicago manufacturing expansion announced
Local government advocates oppose Pritzker plan to cut distributions
New Lenox Fire District Exploring Land Swap with Village for New Training Facility
WATCH: Illinois diversity leaders dodge questions as they slip farther from goals
Illinois Quick Hits: Road fund could help renovate Soldier Field
Planning Commission Backs 5-MW Peotone Solar Farm; Developer Pledges Pollinator Habitat and Community Funds
Joliet Junior College Board Approves $2 Tuition Increase Amidst Heated Debate Over Enrollment and Spending
New Lenox District 122 Kicks Off 2026-2027 Budget Cycle, Approves Minor Registration Fee Increase
New Lenox Park District Outlines Aggressive 2026 Development Plan, Addresses Crossroads Sinkhole
New Lenox Library Explores Rebranding Ahead of 25th Anniversary on the Commons
Lincoln-Way Board Ratifies Three-Year Support Staff Contract with Significant Hourly Raises