Screenshot 2025-10-10 at 11.39.50 AM

Will County’s Gas-to-Energy Plant Reports Nearly $460,000 Net Loss Amid Operational Setbacks

Spread the love

Will County Finance Committee Meeting October 7, 2025

Article Summary: Will County’s Renewable Natural Gas (RNG) plant at the county landfill posted a net loss of nearly $460,000 for the fiscal year through August, after a summer plagued by mechanical failures, power outages, and maintenance issues that hampered production. Despite the challenges, officials remain optimistic about closing the financial gap by the end of the fiscal year, pointing to a strong performance in September and the plant’s long-term revenue potential.

RNG Plant Performance Key Points:

  • As of August 31, 2025, the RNG plant reported a net loss of $459,484.52 for the fiscal year.

  • Production in July and August fell below targets due to valve failures, sensor issues, severe storms, and computer errors.

  • Production exceeded targets in June, and a strong rebound in September has officials hopeful of breaking even for the year.

  • The plant is in its third year of repaying a 12-year, $48 million green bond used for its construction.

JOLIET, IL – Will County’s gas-to-energy plant has faced a series of operational challenges this summer, resulting in a net loss of $459,484 as of August 31, according to a report presented to the Finance Committee on Tuesday, October 7, 2025.

Greg Komperda, the RNG Facility Project Manager, detailed a difficult summer for the plant, which converts landfill gas into pipeline-quality natural gas. While production in June exceeded its target, generating over 73,000 Million British Thermal Units (MMBtu), performance dipped significantly in July and August.

In July, the plant produced 68,768 MMBtu against a target of 71,300 MMBtu. August production fell further to 64,446 MMBtu. Komperda attributed the shortfalls to a string of problems, including:

  • Valve failures in the nitrogen removal system, likely caused by moisture in the compressed air supply.

  • A delivery rejection from the pipeline operator due to faulty sensors at the delivery point.

  • Ongoing landfill wellfield maintenance, which temporarily reduced the flow of gas to the plant.

  • Sporadic power outages caused by severe storms in late August.

  • Computer errors in the nitrogen control system that required the manufacturer to reprogram it.

Despite the setbacks, Komperda reported that production rebounded in September to over 69,000 MMBtu. “We are closing in on the gap,” he said. “If we could maintain production at a good level, we have a chance of closing that gap in on our under revenue.”

Board members questioned the operational reliability and long-term financial viability of the project. In response to questions about frequent power outages, officials stated that installing a backup generator system capable of powering the plant was not financially feasible. Similarly, a significant solar array to offset the plant’s high electricity consumption—more than all other county facilities combined—would require 70-80 acres and cost an estimated $28 to $48 million.

Board member Daniel J. Butler highlighted the project’s long-term investment perspective. He confirmed with officials that the plant was financed with a 12-year, $48 million green bond. With three years of payments made, the facility has nine years of debt service remaining.

“After 12 years, we are going to be having generate extra money and it should lessen the tax burden,” Butler said, framing the current challenges within the context of the plant’s projected 35-plus-year lifespan. “Here we are making an investment into the future for the people of Will County.”

Today Jun 14
Sunny
76° 55°

Sunny

💨 5 to 10 mph 💧 0%

Leave a Comment





Latest News Stories

KidsWork Children’s Museum

KidsWork Children’s Museum to Install New Crane Exhibit

Village of New Lenox Board Meeting | January 12, 2026 Article Summary: Using grant funds from a local solar energy partner, the Village Board authorized the purchase of a new...
New Lenox Park District

New Lenox Park Board Slated to Honor Youth Football and Cheerleading Champions

New Lenox Community Park District Meeting | December 17, 2025 Article Summary: The New Lenox Community Park District Board of Commissioners is scheduled to formally recognize two local youth teams...
Will County Logo Graphic

Northern Builders Development Brings Changes to Laraway and Gougar Roads in New Lenox

Will County Board Meeting | January 15, 2026 Article Summary: The Will County Board approved access permits for a new development by Northern Builders at the intersection of Laraway Road...

Meeting Summary and Briefs: Will County Public Works & Transportation Committee for January 6, 2026

Will County Public Works & Transportation Committee Meeting | January 6, 2026 Meeting SummaryThe Will County Board Public Works & Transportation Committee met on Tuesday, January 6, 2026, to discuss...
Will County Board Graphic.03

County Board Debates Legislative Agendas; State Agenda Passes, Federal Agenda Sent Back

Will County Board Meeting | January 15, 2026 Article Summary: The Will County Board engaged in a vigorous and at times confusing debate over its 2026 legislative priorities, ultimately passing...
lincoln way school district 210 logo.1

District 210 Updates Online Course Policy and Increases Summer School Fees

Lincoln-Way 210 Board of Education Meeting | Jan. 15, 2026 Article Summary: The Board of Education approved an increase in summer school fees and clarified policies regarding online coursework for...
Congratulations to Corporal Kurtis Ingram

Corporal Ingram completes elite leadership training program

Corporal Kurtis Ingram has successfully completed the School of Police Staff and Command (SPSC) at Northwestern University’s Center for Public Safety. The SPSC is an intensive 10-week program focused on...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Executive Committee for January 8, 2026

Will County Board Executive Committee Meeting | January 8, 2026 Overall Meeting SummaryThe Will County Board Executive Committee met on Thursday, January 8, 2026, tackling a heavy agenda that included...
Fire-Ambulance-Rescue-Logo

Automatic Sprinklers Contain Industrial Fire in New Lenox

Article Summary: New Lenox firefighters responded to a machinery fire at a facility on Berens Drive early Tuesday afternoon, where the building's fire suppression system prevented the blaze from spreading....
Pritzker signs Clean Slate Act to automatically seal some criminal convictions

Pritzker signs Clean Slate Act to automatically seal some criminal convictions

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – Gov. J.B. Pritzker has signed legislation to automate the state’s record-sealing process for individuals with certain criminal...
The fire at Woldhuis Sunrise Greenhouse had the mutual aid of 19 other agencies-photo courtesy Woldhuis.

Blaze Destroys Building and Food Truck at Woldhuis Sunrise Nursery

By Andrea Arens A massive fire tore through Woldhuis Sunrise Nursery late Thursday morning, destroying one greenhouse building, a food truck, damaging another building and drawing firefighters from across the...
Will County Board Graphic.02

Freight Clusters Drive Push for Overhaul of Wilmington-Peotone Road; County Advances Broader 2050 Plan

Will County Board Meeting | January 15, 2026 Article Summary: Citing the emergence of "new freight clusters," Will County is seeking federal support for a massive study to redesign 22...
sunny hill nursing home joliet il

Sunny Hill Administrator Defends Private Room Model Amidst Capacity Discussions

Will County Board Public Health & Safety Committee Meeting | January 7, 2026 Article Summary: During the January 7, 2026, meeting, Sunny Hill Nursing Home Administrator Maggie McDowell reported a...
Screenshot 2026-01-13 at 1.54.20 PM

New Lenox Approves Plat for Cherry Hill Triangle Industrial Site

Village of New Lenox Board Meeting | January 12, 2026 Article Summary: The Village Board approved the preliminary and final plat for the Cherry Hill Triangle, a three-lot subdivision designed...
Elite private colleges can’t cap off price-fixing collusion class action

Elite private colleges can’t cap off price-fixing collusion class action

By Scott Holland | Legal NewslineThe Center Square A federal judge in Chicago has refused to end an antitrust class action complaint accusing elite universities of colluding in the financial...