Winter Start Unlikely for $4 Million New Lenox Fire Station 62 Remodel

Spread the love

New Lenox Fire Protection District Meeting | August 2025

Article Summary: The planned $4 million remodel of New Lenox Fire Station 62 faces a potential delay, as officials indicated a winter groundbreaking is unlikely due to logistical challenges. The project has an estimated eight-week timeline, but the need to vacate the station’s apparatus bay for two weeks makes a cold-weather start impractical.

Station 62 Remodel Update Key Points:

  • District officials met with the project’s construction manager for a walk-through of the station.

  • The estimated construction timeline for the project is eight weeks.

  • Chief Adam Riegel stated the apparatus bay would need to be empty for two weeks, which could not be done in the winter.

  • The construction manager is expected to deliver a budget for the project soon.

A winter start for the New Lenox Fire Protection District’s major remodel of Station 62 appears improbable, according to discussions at the Board of Trustees meeting on Monday, August 18, 2025.

While no formal action was taken, district leaders provided an update on the project’s timeline and logistics. Officials reported they had met with the construction manager, Northern Builders, for a walk-through of the station and are expecting a formal budget proposal shortly.

During the discussion, Trustee Levey inquired about the estimated start and end dates for the project. Fire Chief Adam Riegel said the construction itself is estimated to take eight weeks. However, he noted a significant logistical hurdle: the station’s apparatus bay would need to be completely empty for two weeks to allow work to proceed, a scenario he said “we couldn’t do that in the winter.”

Deputy Chief Randolph added that the district is working with the construction team to coordinate timing and figure out staffing and vehicle placement to ensure the station can remain operational during the renovation. This includes lining up the construction schedule with times when fire trucks are already out of service for maintenance. Given these constraints, a groundbreaking before spring appears unlikely.

Events

No events

Leave a Comment





Latest News Stories

Meeting-Briefs

Meeting Briefs: Will County Ad-Hoc Ordinance Review Committee for July 22, 2025

AI Policy Discussion Urged: Chair Jackie Triner called for the county to develop a comprehensive policy on the use of Artificial Intelligence. Citing a recent conference, Triner noted the potential benefits...
New-Lenox-Village-Board.1

New Lenox’s Crossroads Sports Complex Opens to Rave Reviews, On Time and Under Budget

NEW LENOX – The newly opened Crossroads Sports Complex is already proving to be a resounding success, according to a report delivered at the New Lenox Village Board meeting on...
New-Lenox-Village-Board.4

New Lenox Waives Over $13,000 in Permit Fees for Park District, Church Projects

NEW LENOX – The New Lenox Village Board unanimously approved waiving more than $13,000 in permit and plan review fees for two significant community projects during its meeting on Monday....
New-Lenox-Police.3

New Lenox Approves Site Plan for MBPRO Truck Repair on Moni Drive

NEW LENOX – The Village Board on Monday approved site modifications for a new truck repair business, MBPRO Services, set to open at 21660 South Moni Drive. The board unanimously...
Meeting-Briefs

Meeting Summary: New Lenox Board of Trustees for July 14, 2025

The New Lenox Village Board of Trustees met Monday to approve site plans for a new business, waive fees for community projects, and hear a glowing report on the new...
WCO-PZ-July-15

Crete Township Wins Approval for New Digital Sign at Community Center

Crete Township received approval from the Will County Planning and Zoning Commission on Tuesday for a new digital sign at its community center, a project that required a special use...
WCO-PZ-July-15

Will County Planners OK Oversized Garage Near Naperville, Overriding Staff Recommendation

The Will County Planning and Zoning Commission on Tuesday approved variances for a new oversized accessory garage in Wheatland Township, siding with a homeowner and builder over a staff recommendation...
WCO-PZ-July-15

Green Garden Landscaping Business Gains Permit Amid Strong Neighbor Support

A small landscaping and lawn maintenance business operating on a residential property in Green Garden Township received official approval Tuesday after neighbors voiced overwhelming support for the operation. The Will...
Meeting-Briefs

Meeting Briefs: Will County Planning and Zoning Commission for July 15, 2025

Frankfort Shed Relocation Approved: A homeowner on West Harvest Drive in Frankfort Township received a variance to reduce an east side-yard setback from 10 to 4 feet. The variance, sought by...
Frankfort-Village-Board-Meeting-Graphic

Frankfort Approves ‘Whisk & Flame’ Culinary Studio, Slashes Parking Requirement for Downtown Property

An experiential culinary studio named Whisk & Flame is set to open in downtown Frankfort after the Village Board approved a series of special use permits and a significant parking...
Frankfort-Village-Board-Meeting-Graphic

Frankfort Village Board Adopts $59.4 Million Appropriation for Fiscal Year 2026

The Frankfort Village Board has formally set its maximum legal spending limit for the upcoming fiscal year, adopting a $59,366,900 appropriation ordinance for fiscal year 2026. The measure was passed...
Frankfort-Village-Board-Meeting-Graphic

Frankfort Establishes New Zoning Rules to Attract Data Centers

The Village of Frankfort has amended its zoning ordinance to create a specific use category for data centers, a move designed to regulate and attract high-tech development. The Village Board...
Frankfort-Village-Board-Meeting-Graphic

Currie Motors Expansion Gets Approval with Site Modifications

Currie Motors on Lincoln Highway received approval from the Frankfort Village Board on Monday for a major change to its site plan, allowing for the construction of seven new parking...
Frankfort-Village-Board-Meeting-Graphic

Frankfort Approves $134,531 Maintenance Contract for Wastewater Plant Filters

The Frankfort Village Board has approved a $134,531.17 agreement with Veolia Water Technologies, Inc. for critical preventative maintenance at the Regional Wastewater Treatment Plant. The contract is for the complete...
Frankfort-Village-Board-Meeting-Graphic

Meeting Briefs: Frankfort Village Board for July 14, 2025

'Whisk & Flame' Culinary Studio Approved: The board approved "Whisk & Flame," an experiential culinary studio, for 10-12 Elwood Street. The project includes four special use permits for entertainment, liquor sales,...