Winter Start Unlikely for $4 Million New Lenox Fire Station 62 Remodel
New Lenox Fire Protection District Meeting | August 2025
Article Summary: The planned $4 million remodel of New Lenox Fire Station 62 faces a potential delay, as officials indicated a winter groundbreaking is unlikely due to logistical challenges. The project has an estimated eight-week timeline, but the need to vacate the station’s apparatus bay for two weeks makes a cold-weather start impractical.
Station 62 Remodel Update Key Points:
-
District officials met with the project’s construction manager for a walk-through of the station.
-
The estimated construction timeline for the project is eight weeks.
-
Chief Adam Riegel stated the apparatus bay would need to be empty for two weeks, which could not be done in the winter.
-
The construction manager is expected to deliver a budget for the project soon.
A winter start for the New Lenox Fire Protection District’s major remodel of Station 62 appears improbable, according to discussions at the Board of Trustees meeting on Monday, August 18, 2025.
While no formal action was taken, district leaders provided an update on the project’s timeline and logistics. Officials reported they had met with the construction manager, Northern Builders, for a walk-through of the station and are expecting a formal budget proposal shortly.
During the discussion, Trustee Levey inquired about the estimated start and end dates for the project. Fire Chief Adam Riegel said the construction itself is estimated to take eight weeks. However, he noted a significant logistical hurdle: the station’s apparatus bay would need to be completely empty for two weeks to allow work to proceed, a scenario he said “we couldn’t do that in the winter.”
Deputy Chief Randolph added that the district is working with the construction team to coordinate timing and figure out staffing and vehicle placement to ensure the station can remain operational during the renovation. This includes lining up the construction schedule with times when fire trucks are already out of service for maintenance. Given these constraints, a groundbreaking before spring appears unlikely.
Latest News Stories
Meeting Summary and Briefs: New Lenox School District 122 for August 2025
Will County Reverses Zoning on Peotone Farmland to Facilitate 10-Acre Sale
Meeting Summary and Briefs: Joliet Junior College Board of Trustees for September 10, 2025
Lincoln-Way 210 Board Approves $172.7 Million Budget with Planned Deficit for Bus Purchases
Meeting Summary and Briefs: New Lenox Community Park District for August 2025
Pavlov Media to Bring New Fiber Internet Option to New Lenox
Will County to Pay Enbridge $82,000 to Relocate Pipeline Equipment for Exchange Street Improvements
Laraway Road Widening Project in New Lenox and Frankfort Gets Additional $468,000 for Redesign
“Federal Policy Uncertainty” Blamed for Delay of Peotone Solar Farm; County Grants Second Extension
Will County Grants Extensions to Five Solar Projects Sold to New Developers
Will County Board Approves Controversial Drug Recovery Retreat in Crete Township
Winter Start Unlikely for $4 Million New Lenox Fire Station 62 Remodel