Article Summary: The planned $4 million remodel of New Lenox Fire Station 62 faces a potential delay, as officials indicated a winter groundbreaking is unlikely due to logistical challenges. The project has an estimated eight-week timeline, but the need to vacate the station’s apparatus bay for two weeks makes a cold-weather start impractical.
Station 62 Remodel Update Key Points:
-
District officials met with the project’s construction manager for a walk-through of the station.
-
The estimated construction timeline for the project is eight weeks.
-
Chief Adam Riegel stated the apparatus bay would need to be empty for two weeks, which could not be done in the winter.
-
The construction manager is expected to deliver a budget for the project soon.
A winter start for the New Lenox Fire Protection District’s major remodel of Station 62 appears improbable, according to discussions at the Board of Trustees meeting on Monday, August 18, 2025.
While no formal action was taken, district leaders provided an update on the project’s timeline and logistics. Officials reported they had met with the construction manager, Northern Builders, for a walk-through of the station and are expecting a formal budget proposal shortly.
During the discussion, Trustee Levey inquired about the estimated start and end dates for the project. Fire Chief Adam Riegel said the construction itself is estimated to take eight weeks. However, he noted a significant logistical hurdle: the station’s apparatus bay would need to be completely empty for two weeks to allow work to proceed, a scenario he said “we couldn’t do that in the winter.”
Deputy Chief Randolph added that the district is working with the construction team to coordinate timing and figure out staffing and vehicle placement to ensure the station can remain operational during the renovation. This includes lining up the construction schedule with times when fire trucks are already out of service for maintenance. Given these constraints, a groundbreaking before spring appears unlikely.
Latest News Stories
WATCH: Trump calls Pritzker ’nothing’ in public safety push; U.S. Rep. Mary Miller live
Illinois quick hits: Three dead outside Berwyn school; steady economic conditions reported
New Lenox Township Approves 12.5% Increase for Employee Health Insurance
Joliet Junior College, City of Joliet to Explore Joint Public Safety Institute
WATCH: Illinois prison mail scanning rule faces lawmaker scrutiny
New Lenox Scout Prompts Multi-Agency Action on Neighborhood Traffic Safety
Meeting Summary and Briefs: Village of New Lenox Board of Trustees for September 2025
New Lenox Approves Nearly $43,000 in New Kitchen Equipment for Crossroads Sports Complex
New Lenox Extends Deadline for Sale of Maple Street Property
JJC Moves Forward with Major Technology Overhaul to Modernize College Operations
Meeting Summary and Briefs: Joliet Junior College Board of Trustees for August 20, 2025
Tensions Flare as JJC Chairman Rebukes “Entitlement” After Trustee Lists Demands