Winter Start Unlikely for $4 Million New Lenox Fire Station 62 Remodel
New Lenox Fire Protection District Meeting | August 2025
Article Summary: The planned $4 million remodel of New Lenox Fire Station 62 faces a potential delay, as officials indicated a winter groundbreaking is unlikely due to logistical challenges. The project has an estimated eight-week timeline, but the need to vacate the station’s apparatus bay for two weeks makes a cold-weather start impractical.
Station 62 Remodel Update Key Points:
-
District officials met with the project’s construction manager for a walk-through of the station.
-
The estimated construction timeline for the project is eight weeks.
-
Chief Adam Riegel stated the apparatus bay would need to be empty for two weeks, which could not be done in the winter.
-
The construction manager is expected to deliver a budget for the project soon.
A winter start for the New Lenox Fire Protection District’s major remodel of Station 62 appears improbable, according to discussions at the Board of Trustees meeting on Monday, August 18, 2025.
While no formal action was taken, district leaders provided an update on the project’s timeline and logistics. Officials reported they had met with the construction manager, Northern Builders, for a walk-through of the station and are expecting a formal budget proposal shortly.
During the discussion, Trustee Levey inquired about the estimated start and end dates for the project. Fire Chief Adam Riegel said the construction itself is estimated to take eight weeks. However, he noted a significant logistical hurdle: the station’s apparatus bay would need to be completely empty for two weeks to allow work to proceed, a scenario he said “we couldn’t do that in the winter.”
Deputy Chief Randolph added that the district is working with the construction team to coordinate timing and figure out staffing and vehicle placement to ensure the station can remain operational during the renovation. This includes lining up the construction schedule with times when fire trucks are already out of service for maintenance. Given these constraints, a groundbreaking before spring appears unlikely.
Latest News Stories
Meeting Summary and Briefs: New Lenox Fire Protection District for October 2025
County Takes Over “Central Will” Dial-A-Ride in Major Consolidation
New Lenox Food Pantry Reports Busiest Month Ever, Serving Over 1,100 Individuals in September
New Lenox Park District Board Approves 9% Health Insurance Hike, New Truck Lease
Board Denies Appeal for “Tiny Home” RV Living in Crete
JJC Board Censures Trustee Broderick Twice, Denies Request to Restore Good Standing
Will County Board Compromises on Mental Health Levy, Approves $10 Million After Debate
Green Garden’s Wildflower Farm Granted Second Extension for Rural Events Permit
Will County Board Rejects Proposed Tax Hike, Approves 0% Levy Increase in Contentious Vote
Will County Awards $10.4 Million Contract for Bell Road Widening Project
Regional Office of Education Highlights School Safety, New Learning Programs in Update
New Lenox Solar Farm Proposal Advances with Conditions, Following Village and Forest Preserve Input