Winter Start Unlikely for $4 Million New Lenox Fire Station 62 Remodel
New Lenox Fire Protection District Meeting | August 2025
Article Summary: The planned $4 million remodel of New Lenox Fire Station 62 faces a potential delay, as officials indicated a winter groundbreaking is unlikely due to logistical challenges. The project has an estimated eight-week timeline, but the need to vacate the station’s apparatus bay for two weeks makes a cold-weather start impractical.
Station 62 Remodel Update Key Points:
-
District officials met with the project’s construction manager for a walk-through of the station.
-
The estimated construction timeline for the project is eight weeks.
-
Chief Adam Riegel stated the apparatus bay would need to be empty for two weeks, which could not be done in the winter.
-
The construction manager is expected to deliver a budget for the project soon.
A winter start for the New Lenox Fire Protection District’s major remodel of Station 62 appears improbable, according to discussions at the Board of Trustees meeting on Monday, August 18, 2025.
While no formal action was taken, district leaders provided an update on the project’s timeline and logistics. Officials reported they had met with the construction manager, Northern Builders, for a walk-through of the station and are expecting a formal budget proposal shortly.
During the discussion, Trustee Levey inquired about the estimated start and end dates for the project. Fire Chief Adam Riegel said the construction itself is estimated to take eight weeks. However, he noted a significant logistical hurdle: the station’s apparatus bay would need to be completely empty for two weeks to allow work to proceed, a scenario he said “we couldn’t do that in the winter.”
Deputy Chief Randolph added that the district is working with the construction team to coordinate timing and figure out staffing and vehicle placement to ensure the station can remain operational during the renovation. This includes lining up the construction schedule with times when fire trucks are already out of service for maintenance. Given these constraints, a groundbreaking before spring appears unlikely.
Latest News Stories
County Expands Paratransit Services, Board Members Question Long-Term Funding
California attorney general joins coalition to protect trans youth in sports
Supreme Court blocks National Guard deployment to Chicago
Chicago mayor refuses to sign or veto budget at ‘not a campaign event’
Illinois quick hits: DOJ sues over sanctuary expansion law
Meeting Summary and Briefs: Joliet Junior College Board for Dec. 10, 2025
District 210 Awards $24.4 Million Contract for Major HVAC Upgrades
IL Medicaid overhaul effective Jan. 1 sparks backlash
Illinois quick hits: Man convicted of drug money laundering; human trafficking arrests made
New Lenox Approves 50/50 Gaming Revenue Split for Sports Complex
Mental Health Board Updates Committee on 2026 Grant Cycle and Funding Priorities
PZC Approves Homer Township Landscape Business Despite Neighbor Concerns; Adds Berm Condition