Will County Grants Extensions to Five Solar Projects Sold to New Developers

Spread the love

Article Summary: The Will County Board approved first-time permit extensions for five commercial solar projects across Monee, Crete, and Joliet townships, all of which were recently sold to larger energy developers. The new operators, Nautilus Solar and Madison Energy Infrastructure, now have until 2026 to begin construction as they work to secure final permits.

Solar Project Sales Key Points:

  • Projects Involved: Five separate solar farms in Peotone, Monee, Crete, and Joliet townships received 180-day extensions.

  • New Developers: Two projects were sold to Nautilus Solar, and three were sold to Madison Energy Infrastructure.

  • Action: The extensions give the new owners until February or April 2026 to secure construction permits and lawfully establish the facilities.

  • Status: While required variances for the projects have been established, construction permits submitted by the new developers remain under review by the county.

JOLIET — A pattern of smaller solar energy projects being sold to larger developers has prompted the Will County Board to grant permit extensions for five separate solar farms. The board unanimously approved the first 180-day extensions for the projects, which are now owned by Nautilus Solar and Madison Energy Infrastructure.

According to county memos, the original applicants for all five projects had successfully established required variances related to ground cover and mowing, but the special use permits were nearing their two-year expiration dates. The projects were subsequently sold to the new developers, who have since applied for construction permits that are still under review.

Nautilus Solar acquired two projects:

  • A facility from Aequo Foundation, Inc. on Kennedy Road in Peotone.

  • A facility from Felipe D. Recendez on South Will Center Road in Monee.
    Both permits are now valid through April 17, 2026.

Madison Energy Infrastructure acquired three projects:

  • Two facilities from Dart Farms, Inc. in Joliet Township at the northwest and southwest corners of Cherry Hill Road and W. Schweitzer Road/US 52.

  • A facility from The Moeller Trust on Torrence Avenue in Crete.
    These permits are now valid through February 13, 2026.

The board’s approval of the extensions provides the new operators additional time to finalize the permitting process and begin construction on the renewable energy facilities.

Events

No events

Leave a Comment





Latest News Stories

Pritzker: Fair maps in Illinois would be 'disarming' to Democrats

Pritzker: Fair maps in Illinois would be ‘disarming’ to Democrats

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – Illinois Gov. J.B. Pritzker says Democrats would be “disarming” if they agreed to fair maps state by...
States sue over Victims of Crime Act grant funding

States sue over Victims of Crime Act grant funding

By Elyse Apel | The Center SquareThe Center Square (The Center Square) — Colorado Attorney General Phil Weiser has joined a 20-state coalition and Washington, D.C., suing the Trump administration...
Illinois quick hits: COVID fraud indictments issued; man sentenced for mailing fentanyl

Illinois quick hits: COVID fraud indictments issued; man sentenced for mailing fentanyl

By Jim Talamonti | The Center SquareThe Center Square COVID fraud indictments issued A federal grand jury has indicted four Chicago-area individuals accused of fraudulently obtaining millions of dollars in...
WATCH: Illinois In Focus Daily | Thursday Aug. 21st, 2025

WATCH: Illinois In Focus Daily | Thursday Aug. 21st, 2025

By Greg Bishop | The Center SquareThe Center Square (The Center Square) – In today's edition of Illinois in Focus Daily, The Center Square Editor Greg Bishop shares comments from...
solar panels photovoltaics in solar farm

Will County P&Z Approves Crete Solar Farm, Overruling Township’s General Opposition

Article Summary: The Will County Planning and Zoning Commission recommended approval for a new commercial solar farm in Crete Township, moving the project forward despite being informed by staff of...
P&Z 8.19.25

Will County Board Approves Controversial Recovery Retreat in Crete Township Amid Strong Resident Opposition

Article Summary: The Will County Planning and Zoning Commission approved a special use permit for a long-term residential recovery program on a 68-acre horse farm, despite vocal opposition from Crete...

Will County P&Z: Green Garden Township Variances Granted in Monee

Roy F. Erikson received unanimous approval for two variances for his property at 26409 S. 80th Avenue in Monee. The Will County Planning and Zonning Commission approved reducing the minimum...

Will County P&Z: Manhattan Township Rezoning Approved

The Will County Planning and Zonning Commission unanimously approved a map amendment for a vacant property on South Kankakee Street in Manhattan Township. The request, brought by James and Julie...
Planning & Zoning Graphic.4

Will County P&Z: Green Garden Township Rezoning Approved Amid Concerns Over Lack of a Final Plan

Article Summary: The Will County Planning and Zoning Commission unanimously approved rezoning a large agricultural parcel in Green Garden Township for potential residential development, despite a township official expressing concern...
Two orange map markers on city map

Zoning Commission Overrules Staff, Approves Greeen Garden Twp Variance for 3-Acre Agricultural Lot

Article Summary: The Will County Planning and Zoning Commission approved a variance for a 3-acre lot in an agricultural zone, going against a staff recommendation to deny the request in...
Clearwave

Village-Wide Broadband Service Coming as New Lenox Approves Clearwave Fiber Agreement

Article Summary: New Lenox residents will soon have a new choice for internet service after the Village Board approved a right-of-way use agreement with Clearwave Fiber, which plans to build...
LW SB AUG.1

Lincoln-Way Board Approves Special Education Co-op Budget Amid Concerns Over Rising Costs

Article Summary: The Lincoln-Way District 210 Board of Education approved the Fiscal Year 2026 budget for the Lincoln-Way Special Education District 843 cooperative, while officials expressed concern over significant cost...
LW-SB-AUG.1

Lincoln-Way Board Approves Special Education Co-op Budget Amid Concerns Over Rising Costs

Article Summary: The Lincoln-Way District 210 Board of Education approved the Fiscal Year 2026 budget for the Lincoln-Way Special Education District 843 cooperative, while officials expressed concern over significant cost...
Illinois trucker warns foreign firms faking logs, dodging rules, risking safety

Illinois trucker warns foreign firms faking logs, dodging rules, risking safety

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – After a recent deadly crash in Florida and a crash in Illinois involving semi-trucks, an Illinois...
Illinois law mandates pharmacies to sell needles, sparking safety debate

Illinois law mandates pharmacies to sell needles, sparking safety debate

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – The Illinois Governor has signed House Bill 2589, which requires pharmacists to sell sterile hypodermic needles...