New Lenox School District 122 Approves $908,900 Equipment Purchase for Tyler Elementary HVAC Overhaul

Spread the love

Meeting Summary and Briefs: New Lenox School District 122 Meeting | August 2025

Article Summary: The New Lenox School District 122 Board of Education has authorized the pre-purchase of $908,900 in HVAC equipment for a major renovation at Tyler Elementary School, slated for the summer of 2026. The total project, estimated at over $8.1 million, will modernize the school’s 1980s-era heating and cooling systems and include numerous other building upgrades.

Tyler HVAC Renovation Key Points:

  • The board approved a $908,900 equipment order through the OMNIA Partners Purchasing Cooperative.

  • The total projected cost for the renovation, including installation and other improvements, is $8,148,000.

  • The project will replace the school’s original 1980 heating infrastructure with a modern, energy-efficient V.R.F. system.

  • Additional upgrades will include new ceilings, dimmable LED lighting, a new Public Address system, and a new Fire Alarm System.

The New Lenox School District 122 Board of Education on Tuesday, August 19, 2025, approved a significant first step in a multi-million dollar renovation of Tyler Elementary School, authorizing the pre-purchase of $908,900 in new HVAC equipment. The total project, with an estimated cost of $8,148,000, aims to completely overhaul the school’s mechanical systems during the summer of 2026.

Business Manager/CSBO Robert Groos explained that the equipment must be purchased well in advance to ensure it is delivered before installation work begins. The district is using the OMNIA Partners Purchasing Cooperative to comply with state purchasing laws while securing competitive pricing.

Rob Wroble of Legat Architects presented the project’s design and timeline to the board, detailing the necessity of the upgrades. “Tyler School relies on the original heating system infrastructure which dates back to 1980 when the building was opened,” Wroble’s presentation noted, identifying Tyler as the last of four older district schools to receive such a modernization.

The current system is supplied by centralized hot water boilers and uses original pneumatic tubing, valves, and thermostats for temperature control. The aging infrastructure also includes two air-cooled condensing units and cabinet unit ventilators that are beyond their life expectancy.

The proposed replacement is a Variable Refrigerant Flow (V.R.F.) mechanical system, which separates heating and cooling from ventilation. This design is more energy-efficient as it reduces the need to pre-heat or cool large amounts of outside air. Instead of a boiler and chiller, the V.R.F. system uses heat pumps and circulates refrigerant through a two-pipe network to fan coil units in each room. The district is already familiar with this technology, as it is currently operating in three other schools.

Benefits of the new system, according to the presentation, include lower operating costs, smaller equipment, and excellent temperature and humidity control, with thermostats located in every room.

Beyond the mechanical overhaul, the project will fund a host of other improvements throughout the school. These include new bookshelves and storage cabinets in every classroom, new ceilings with dimmable LED light fixtures, a new Public Address System, and a new Fire Alarm System.

During the meeting, board members asked clarifying questions about the project’s logistics. Member Al Haring inquired about equipment storage, to which Mr. Wroble confirmed it would be stored off-site by the contractor or a third party. In response to a question from Member Nicole DeGrave, Wroble noted that while different companies installed the V.R.F. systems at other schools, the equipment and warranties are the same, ensuring consistency.

The project timeline calls for the board to approve the final construction contracts in December 2025. Final bond financing options to fund the project will be reviewed and approved by the board later in the fall of 2025.

Events

No events

Leave a Comment





Latest News Stories

default

Lincoln-Way School Board Certifies Election, Re-elects Janik as President

The Lincoln-Way Community High School District 210 Board of Education officially reorganized for the upcoming year during its meeting on April 17, certifying the results of the April 1 consolidated...
lincoln-way-school-district

New Electricity Contract to Save Lincoln-Way Over $500,000 Next Year

Lincoln-Way High School District 210 is poised for significant energy cost savings after the Board of Education unanimously approved a new 54-month electric commodity contract with Direct Energy. The agreement,...
frankfort-square-park-district.1

Four New Commissioners to Join Frankfort Square Park District Board in May

Four newly elected commissioners are set to join the Frankfort Square Park District Board in May, following the April 1, 2025, Consolidated Election. Executive Director Audrey Marcquenski formally congratulated Lauren...
Meeting-Briefs

Meeting Briefs: Frankfort Square Park District for April 17, 2025

The Frankfort Square Park District Board of Commissioners met on April 17 to approve its annual budget, discuss new projects, and hear departmental updates. The district approved a nearly $5...
lincoln-way-school-district.3-scaled-e1750128024313

Lincoln-Way District 210 Board Briefs

District Finances Stable in March ReportAssistant Superintendent Michael Duback presented the Treasurer’s Report for the month ending March 31, 2025. Revenues for the month totaled $3.1 million, while expenditures were...
Frankfort-Township-Logo-Graphic

Frankfort Township Board Unanimously Opposes Government Consolidation

The Frankfort Township Board on Monday took a firm stance against a perennial issue in Illinois politics, unanimously passing a resolution to formally oppose any legislative efforts to consolidate or...
Frankfort-Township-Logo-Graphic

Frankfort Township Upgrading Senior Apartments Amidst High Demand

Frankfort Township is moving forward with significant upgrades to its senior apartments to meet modern standards, Supervisor Nick George announced at Monday’s board meeting. The improvements come as the township...
Frankfort-Township-Logo-Graphic

Outdoor Bar Expansion Gets Green Light from Frankfort Township

The Frankfort Township Board has approved a special use permit that will allow a bar in an unincorporated area to expand its service outdoors. The unanimous decision was made during...
Frankfort-Township-Logo-Graphic

Meeting Briefs: Frankfort Township Board for April 14, 2025

The Frankfort Township Board of Trustees met on Monday, April 14, 2025, to address zoning matters and new business. The board took a firm stance against government consolidation, unanimously passing...