New-Lenox-School-122.6

New Lenox School District 122 Approves $908,900 Equipment Purchase for Tyler Elementary HVAC Overhaul

Spread the love

Meeting Summary and Briefs: New Lenox School District 122 Meeting | August 2025

Article Summary: The New Lenox School District 122 Board of Education has authorized the pre-purchase of $908,900 in HVAC equipment for a major renovation at Tyler Elementary School, slated for the summer of 2026. The total project, estimated at over $8.1 million, will modernize the school’s 1980s-era heating and cooling systems and include numerous other building upgrades.

Tyler HVAC Renovation Key Points:

  • The board approved a $908,900 equipment order through the OMNIA Partners Purchasing Cooperative.

  • The total projected cost for the renovation, including installation and other improvements, is $8,148,000.

  • The project will replace the school’s original 1980 heating infrastructure with a modern, energy-efficient V.R.F. system.

  • Additional upgrades will include new ceilings, dimmable LED lighting, a new Public Address system, and a new Fire Alarm System.

The New Lenox School District 122 Board of Education on Tuesday, August 19, 2025, approved a significant first step in a multi-million dollar renovation of Tyler Elementary School, authorizing the pre-purchase of $908,900 in new HVAC equipment. The total project, with an estimated cost of $8,148,000, aims to completely overhaul the school’s mechanical systems during the summer of 2026.

Business Manager/CSBO Robert Groos explained that the equipment must be purchased well in advance to ensure it is delivered before installation work begins. The district is using the OMNIA Partners Purchasing Cooperative to comply with state purchasing laws while securing competitive pricing.

Rob Wroble of Legat Architects presented the project’s design and timeline to the board, detailing the necessity of the upgrades. “Tyler School relies on the original heating system infrastructure which dates back to 1980 when the building was opened,” Wroble’s presentation noted, identifying Tyler as the last of four older district schools to receive such a modernization.

The current system is supplied by centralized hot water boilers and uses original pneumatic tubing, valves, and thermostats for temperature control. The aging infrastructure also includes two air-cooled condensing units and cabinet unit ventilators that are beyond their life expectancy.

The proposed replacement is a Variable Refrigerant Flow (V.R.F.) mechanical system, which separates heating and cooling from ventilation. This design is more energy-efficient as it reduces the need to pre-heat or cool large amounts of outside air. Instead of a boiler and chiller, the V.R.F. system uses heat pumps and circulates refrigerant through a two-pipe network to fan coil units in each room. The district is already familiar with this technology, as it is currently operating in three other schools.

Benefits of the new system, according to the presentation, include lower operating costs, smaller equipment, and excellent temperature and humidity control, with thermostats located in every room.

Beyond the mechanical overhaul, the project will fund a host of other improvements throughout the school. These include new bookshelves and storage cabinets in every classroom, new ceilings with dimmable LED light fixtures, a new Public Address System, and a new Fire Alarm System.

During the meeting, board members asked clarifying questions about the project’s logistics. Member Al Haring inquired about equipment storage, to which Mr. Wroble confirmed it would be stored off-site by the contractor or a third party. In response to a question from Member Nicole DeGrave, Wroble noted that while different companies installed the V.R.F. systems at other schools, the equipment and warranties are the same, ensuring consistency.

The project timeline calls for the board to approve the final construction contracts in December 2025. Final bond financing options to fund the project will be reviewed and approved by the board later in the fall of 2025.

Leave a Comment





Latest News Stories

Lincoln Way Central Softball Graphic

Lincoln-Way East Powers Past Knights in Conference Clash

The Lincoln-Way Central varsity softball team struggled to contain a high-powered Lincoln-Way East offense on Thursday, falling 15-1 in a conference matchup at home. Lincoln-Way East jumped out to an...
Lincoln Way Central Baseball Graphic

Mid-Game Rally Falls Short as Lincoln-Way Central Drops 7-4 Contest to Lincoln-Way East

Despite a spirited mid-game surge that cut a six-run deficit to two, the Lincoln-Way Central varsity baseball team could not complete the comeback, falling 7-4 to visiting conference rival Lincoln-Way...
NYC schools probed over claims of antisemitism

NYC schools probed over claims of antisemitism

By Chris WadeThe Center Square The Trump administration is investigating claims that New York City schools violated the civil rights of Jewish students by hosting seminars on Palestinian resistance. The...
Illinois Quick Hits: AFP says tax breaks would be more at Soldier Field

Illinois Quick Hits: AFP says tax breaks would be more at Soldier Field

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – Americans for Prosperity Illinois says megaprojects legislation that cleared the Illinois House could give a proposed development...
Soldier's insider trading case puts prediction markets to the test

Soldier’s insider trading case puts prediction markets to the test

By Brett RowlandThe Center Square An alleged attempt by a U.S. Army Special Forces soldier to profit from classified military intelligence on a prediction market platform has resulted in the...
U.S. will continue blockade 'as long as it takes,' Hegseth says

U.S. will continue blockade ‘as long as it takes,’ Hegseth says

By Andrew RiceThe Center Square The United States will continue it's blockade in the Strait of Hormuz for "as long as it takes," War Secretary Pete Hegseth said on Friday....
Will County Board Graphic.03

Will County Takes Jurisdiction of Countyline Road in $1.84 Million Agreement with Kankakee County

Will County Board Meeting | April 16, 2026 Article Summary: The Will County Board has approved a jurisdictional transfer that brings a 4.27-mile stretch of Countyline Road entirely under Will...
Will County Board Graphic.01

Green Garden Township’s Wildflower Farm Granted Third Special Use Extension

Will County Board Meeting | April 16, 2026 Article Summary: Bengston Land Management, LLC secured a third extension on its special use permit to host rural events at The Wildflower...
Gori seeks quick end to asbestos fraud, lawsuit ‘bounties' case

Gori seeks quick end to asbestos fraud, lawsuit ‘bounties’ case

By Jonathan Bilyk | Legal NewslineThe Center Square The Gori Law Firm, considered America’s most prolific filer of asbestos personal injury lawsuits, has pushed back on claims it engaged in...
Texas Ten Commandments law may reach Supreme Court

Texas Ten Commandments law may reach Supreme Court

By Esther WickhamThe Center Square A federal appeals court ruling upholding a Texas law requiring Ten Commandments displays in public school classrooms is setting up a potential challenge before the...
Feds reopen probe into LAUSD race-based program

Feds reopen probe into LAUSD race-based program

By Esther WickhamThe Center Square The U.S. Department of Education’s Office for Civil Rights has reopened an investigation into the Los Angeles Unified School District’s Black Student Achievement Plan following...
Trump won't be rushed on Iran as clock ticking for the regime

Trump won’t be rushed on Iran as clock ticking for the regime

By Sarah Roderick-FitchThe Center Square Time is ticking for Iran, as President Donald Trump says he won’t be rushed into giving a timeline regarding the conflict and ceasefire with Iran....
Screenshot 2026-05-10 at 4.26.42 PM

Marathon Petroleum to Cover Contaminated Soil Removal Costs During New Lenox Water Plant Construction

New Lenox Village Board of Trustees Meeting | April 13, 2026 Article Summary: The New Lenox Village Board heard the first reading of an ordinance prohibiting potable water wells near...
Multiple House Republicans defy proposed 3-year FISA Section 702 extension

Multiple House Republicans defy proposed 3-year FISA Section 702 extension

By Thérèse BoudreauxThe Center Square After two attempts last week to reauthorize a controversial spy power of the federal government, House Speaker Mike Johnson, R-La., has unveiled the text of...
Fetterman wants SNAP to cover hot rotisserie chicken

Fetterman wants SNAP to cover hot rotisserie chicken

By John ColeThe Center Square U.S. Sen. John Fetterman, D-Pa., and three of his colleagues have introduced a bill that would allow beneficiaries in the Supplemental Nutrition Assistance Program, or...