New Lenox School District 122 Approves $908,900 Equipment Purchase for Tyler Elementary HVAC Overhaul

Spread the love

Meeting Summary and Briefs: New Lenox School District 122 Meeting | August 2025

Article Summary: The New Lenox School District 122 Board of Education has authorized the pre-purchase of $908,900 in HVAC equipment for a major renovation at Tyler Elementary School, slated for the summer of 2026. The total project, estimated at over $8.1 million, will modernize the school’s 1980s-era heating and cooling systems and include numerous other building upgrades.

Tyler HVAC Renovation Key Points:

  • The board approved a $908,900 equipment order through the OMNIA Partners Purchasing Cooperative.

  • The total projected cost for the renovation, including installation and other improvements, is $8,148,000.

  • The project will replace the school’s original 1980 heating infrastructure with a modern, energy-efficient V.R.F. system.

  • Additional upgrades will include new ceilings, dimmable LED lighting, a new Public Address system, and a new Fire Alarm System.

The New Lenox School District 122 Board of Education on Tuesday, August 19, 2025, approved a significant first step in a multi-million dollar renovation of Tyler Elementary School, authorizing the pre-purchase of $908,900 in new HVAC equipment. The total project, with an estimated cost of $8,148,000, aims to completely overhaul the school’s mechanical systems during the summer of 2026.

Business Manager/CSBO Robert Groos explained that the equipment must be purchased well in advance to ensure it is delivered before installation work begins. The district is using the OMNIA Partners Purchasing Cooperative to comply with state purchasing laws while securing competitive pricing.

Rob Wroble of Legat Architects presented the project’s design and timeline to the board, detailing the necessity of the upgrades. “Tyler School relies on the original heating system infrastructure which dates back to 1980 when the building was opened,” Wroble’s presentation noted, identifying Tyler as the last of four older district schools to receive such a modernization.

The current system is supplied by centralized hot water boilers and uses original pneumatic tubing, valves, and thermostats for temperature control. The aging infrastructure also includes two air-cooled condensing units and cabinet unit ventilators that are beyond their life expectancy.

The proposed replacement is a Variable Refrigerant Flow (V.R.F.) mechanical system, which separates heating and cooling from ventilation. This design is more energy-efficient as it reduces the need to pre-heat or cool large amounts of outside air. Instead of a boiler and chiller, the V.R.F. system uses heat pumps and circulates refrigerant through a two-pipe network to fan coil units in each room. The district is already familiar with this technology, as it is currently operating in three other schools.

Benefits of the new system, according to the presentation, include lower operating costs, smaller equipment, and excellent temperature and humidity control, with thermostats located in every room.

Beyond the mechanical overhaul, the project will fund a host of other improvements throughout the school. These include new bookshelves and storage cabinets in every classroom, new ceilings with dimmable LED light fixtures, a new Public Address System, and a new Fire Alarm System.

During the meeting, board members asked clarifying questions about the project’s logistics. Member Al Haring inquired about equipment storage, to which Mr. Wroble confirmed it would be stored off-site by the contractor or a third party. In response to a question from Member Nicole DeGrave, Wroble noted that while different companies installed the V.R.F. systems at other schools, the equipment and warranties are the same, ensuring consistency.

The project timeline calls for the board to approve the final construction contracts in December 2025. Final bond financing options to fund the project will be reviewed and approved by the board later in the fall of 2025.

Leave a Comment





Latest News Stories

Screenshot-2025-08-13-at-2.15.28-PM

Monee to Receive $250,000 Donation in Solar Project Agreement

Article Summary: The Village of Monee will receive a $250,000 donation from TPE IL W1202, LLC, after the Village Board authorized a community benefit agreement for a planned 5-megawatt solar...
new-lenox-park-district.6

New Lenox Park District Board Approves 2025-2026 Budget

NEW LENOX – The New Lenox Community Park District Board of Commissioners unanimously approved the budget and appropriation ordinance for the 2025-2026 fiscal year during its regular meeting on June...
New-Lenox-School-122.6

Staffing Shortage Leads D122 to Renew Contract for School Psychologist

Facing a persistent staffing shortage for a critical role, the New Lenox School District 122 Board of Education has renewed its contract with an outside agency to provide a school...
Meeting-Briefs

Meeting Summary: New Lenox Township for June 12, 2025

At its June 12 meeting, the New Lenox Township Board of Trustees heard reports on rising demand for community services, discussed ongoing maintenance projects, and assigned responsibilities to its newly...
New-Lenox-Village-Board.4

New Lenox Approves Major Residential Subdivision, Paves Way for Route 6 Commercial Growth

NEW LENOX – The Village Board took decisive action on two major developments Monday, giving final approval to a 55-lot residential subdivision for "empty nesters" and clearing a key hurdle...
New-Lenox-Sharons-Bay-Park

Contractor Selected for Sharon’s Bay Park Redevelopment

NEW LENOX – The New Lenox Community Park District is moving forward with plans to redevelop Sharon's Bay Park, having approved a contractor for the project at its Wednesday meeting....
New-Lenox-Sharons-Bay-Park

Contractor Selected for Sharon’s Bay Park Redevelopment

NEW LENOX – The New Lenox Community Park District is moving forward with plans to redevelop Sharon's Bay Park, having approved a contractor for the project at its Wednesday meeting....
New-Lenox-School-122.5

Handbook Changes at D122 Include Swapping PSAT for PreACT

Students in New Lenox School District 122 will see several changes in the upcoming school year, as the Board of Education approved updates to the 2025-2026 Parent/Student Handbook that affect...
New-Lenox-Police.3

New Dining Options Coming as Village Approves Hot Dog Stand, Restaurant Patio

NEW LENOX – The local dining scene is set for a boost after the Village Board on Monday approved plans for a new hot dog stand and an outdoor patio...
Meeting-Briefs

Meeting Summary: New Lenox Park District for June 18, 2025

The New Lenox Community Park District Board of Commissioners met on June 18, 2025, to approve its annual budget, advance key park projects, and hear updates on a wide range...
Screenshot-2025-08-13-at-2.11.44-PM

Monee Board Sets Spending Plan with 2025-2026 Appropriations Ordinance

Article Summary: The Monee Village Board has approved its annual appropriations ordinance, which acts as the village's legal spending authority for the fiscal year that began May 1, 2025. The...
New-Lenox-School-122.3

New Lenox School District 122 Honors State Track and Field Athletes

New Lenox School District 122 took time during its June 17 board meeting to celebrate the outstanding achievements of its junior high athletes at the 2025 IESA State Track and...

Fiber Optic Internet Competition Coming to New Lenox

NEW LENOX – Residents may soon have a new choice for high-speed internet, as Champaign-based Pavlov Media announced its intention to build out a fiber optic network across the village....
Screenshot-2025-08-13-at-2.15.28-PM

Monee Officials Issue Pool Safety Alert Amid Summer Heat

Article Summary: Following an increase in new pool installations, Monee's Building Services department is reminding residents of mandatory permit and safety requirements. Officials are emphasizing life-safety measures to prevent drownings,...
New-Lenox-Village-Board

Village Board Approves Millions in Spending on Roads, Parks, and Museum

NEW LENOX – The New Lenox Village Board authorized millions of dollars in spending on Monday for its annual road program and for continued investment in its newest community amenities,...