New Lenox School District 122 Approves $908,900 Equipment Purchase for Tyler Elementary HVAC Overhaul

Spread the love

Meeting Summary and Briefs: New Lenox School District 122 Meeting | August 2025

Article Summary: The New Lenox School District 122 Board of Education has authorized the pre-purchase of $908,900 in HVAC equipment for a major renovation at Tyler Elementary School, slated for the summer of 2026. The total project, estimated at over $8.1 million, will modernize the school’s 1980s-era heating and cooling systems and include numerous other building upgrades.

Tyler HVAC Renovation Key Points:

  • The board approved a $908,900 equipment order through the OMNIA Partners Purchasing Cooperative.

  • The total projected cost for the renovation, including installation and other improvements, is $8,148,000.

  • The project will replace the school’s original 1980 heating infrastructure with a modern, energy-efficient V.R.F. system.

  • Additional upgrades will include new ceilings, dimmable LED lighting, a new Public Address system, and a new Fire Alarm System.

The New Lenox School District 122 Board of Education on Tuesday, August 19, 2025, approved a significant first step in a multi-million dollar renovation of Tyler Elementary School, authorizing the pre-purchase of $908,900 in new HVAC equipment. The total project, with an estimated cost of $8,148,000, aims to completely overhaul the school’s mechanical systems during the summer of 2026.

Business Manager/CSBO Robert Groos explained that the equipment must be purchased well in advance to ensure it is delivered before installation work begins. The district is using the OMNIA Partners Purchasing Cooperative to comply with state purchasing laws while securing competitive pricing.

Rob Wroble of Legat Architects presented the project’s design and timeline to the board, detailing the necessity of the upgrades. “Tyler School relies on the original heating system infrastructure which dates back to 1980 when the building was opened,” Wroble’s presentation noted, identifying Tyler as the last of four older district schools to receive such a modernization.

The current system is supplied by centralized hot water boilers and uses original pneumatic tubing, valves, and thermostats for temperature control. The aging infrastructure also includes two air-cooled condensing units and cabinet unit ventilators that are beyond their life expectancy.

The proposed replacement is a Variable Refrigerant Flow (V.R.F.) mechanical system, which separates heating and cooling from ventilation. This design is more energy-efficient as it reduces the need to pre-heat or cool large amounts of outside air. Instead of a boiler and chiller, the V.R.F. system uses heat pumps and circulates refrigerant through a two-pipe network to fan coil units in each room. The district is already familiar with this technology, as it is currently operating in three other schools.

Benefits of the new system, according to the presentation, include lower operating costs, smaller equipment, and excellent temperature and humidity control, with thermostats located in every room.

Beyond the mechanical overhaul, the project will fund a host of other improvements throughout the school. These include new bookshelves and storage cabinets in every classroom, new ceilings with dimmable LED light fixtures, a new Public Address System, and a new Fire Alarm System.

During the meeting, board members asked clarifying questions about the project’s logistics. Member Al Haring inquired about equipment storage, to which Mr. Wroble confirmed it would be stored off-site by the contractor or a third party. In response to a question from Member Nicole DeGrave, Wroble noted that while different companies installed the V.R.F. systems at other schools, the equipment and warranties are the same, ensuring consistency.

The project timeline calls for the board to approve the final construction contracts in December 2025. Final bond financing options to fund the project will be reviewed and approved by the board later in the fall of 2025.

Leave a Comment





Latest News Stories

Arizona recommends measles vaccine during outbreak

Arizona recommends measles vaccine during outbreak

By Chris WoodwardThe Center Square Arizona is recommending vaccinations to combat the state's worst measles outbreak since the 1990s. The latest update this week showed the state has 111 cases...
Govt. shutdown leads to over 800 flights cancelled, number growing

Govt. shutdown leads to over 800 flights cancelled, number growing

By Thérèse BoudreauxThe Center Square As the government shutdown drags into its 38th day and forced flight reductions begin taking effect, the number of daily flight cancellations Americans are experiencing...
Illinois approves $1.5B transit package, funding for long-delayed projects

Illinois approves $1.5B transit package, funding for long-delayed projects

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – Illinois lawmakers approved a $1.5 billion transit package, including long-delayed Moline-to-Chicago rail, hailed by Democrats as...
Supreme Court allows Trump to withhold partial SNAP payment

Supreme Court allows Trump to withhold partial SNAP payment

By Brett RowlandThe Center Square The Supreme Court said Friday that the Trump administration could withhold a partial payment for the federal food benefits program amid the longest-ever government shutdown....
Illinois quick hits: State EPA looks to fund EV charging stations; Tax Foundation says mayor's proposal would hinder employment;

Illinois quick hits: State EPA looks to fund EV charging stations; Tax Foundation says mayor’s proposal would hinder employment;

By Jim Talamonti | The Center SquareThe Center Square State EPA looks to fund EV charging stations The Illinois Environmental Protection Agency (EPA) has announced an Electric Vehicle (EV) Charging...
Congressional Perks: Committees, caucuses cost $50 million since 2019

Congressional Perks: Committees, caucuses cost $50 million since 2019

By Arthur KaneThe Center Square Since 2019, partisan and special interest caucuses and coalitions in the U.S. House spent at least $50 million for staff, food, travel and other expenses,...
Screenshot 2025-11-06 at 4.17.15 PM

Federal Lobbyists Brief Will County on Government Shutdown, Warn of SNAP and TSA Disruptions

Meeting Summary and Briefs: Will County Legislative Committee for November 4, 2025 Article Summary: Will County’s federal lobbyists reported that the ongoing government shutdown, now the longest in U.S. history, is...
New-Lenox-Village-Board.2

New Lenox Residents Plead for Help in Escalating Neighborhood Dispute

New Lenox Village Board Meeting | October 27, 2025 Article Summary: A New Lenox couple made an emotional plea to the Village Board, detailing a year-long dispute with a neighbor that...
Will County Logo Graphic

Commission Approves Mokena-Area Garage Variance Over Village’s Objection

Will County Planning and Zoning Commission Meeting | November 4, 2025 Article Summary: The Will County Planning and Zoning Commission approved a variance for a new garage in unincorporated Frankfort Township...
Screenshot 2025-11-05 at 4.02.49 PM

Will County Committee Advances Gougar Road Bridge Project with Over $540,000 in Agreements

Will County Public Works & Transportation Committee Meeting | November 2025 Article Summary: The Will County Board approved two key agreements for the Gougar Road bridge project in New Lenox,...
Joliet-Junior-college.-Graphic-Logo.4

JJC Receives Surprise $1.9 Million from IRS Employee Retention Credit

Joliet Junior College Board of Trustees Meeting | October 15, 2025 Article SummaryJoliet Junior College has received an unexpected $1.9 million windfall from the federal Employee Retention Credit (ERC), a...
Joliet-Junior-college.-Graphic-Logo.2

JJC Advances ERP Modernization with New Vendor and Two-Year Budget

Joliet Junior College Board of Trustees Meeting | October 15, 2025 Article SummaryJoliet Junior College is entering the next phase of its Enterprise Resource Planning (ERP) system overhaul, with the...
new-lenox-fire-district-stations.3

Station 62 Remodel Advances as Fire District Seeks to Waive Permit Fees

New Lenox Fire Protection District Meeting | September 2025 Article Summary: The planned remodel of New Lenox Fire Station 62 is moving into its next phase, with officials having completed...
Screenshot 2025-11-06 at 4.17.02 PM

Will County Committee Shapes 2026 Legislative Agendas on Housing, Energy, and Health

Meeting Summary and Briefs: Will County Legislative Committee for November 4, 2025 Article Summary: The Will County Legislative Committee advanced key priorities for its 2026 state and federal legislative agendas, focusing...
New-Lenox-School-122.3

New Lenox School District 122 Considers Community Solar Program Promising $55K in Annual Savings

New Lenox School District 122 Meeting | September 2025 Article Summary: New Lenox School District 122 is exploring a 20-year subscription to a community solar program that could save the...