New Lenox Fire District Approves Contract for $4 Million Station 62 Remodel
New Lenox Fire Protection District Meeting | July 2025
Article Summary: The New Lenox Fire Protection District Board of Trustees has approved a contract with Northern Builders to manage the upcoming addition and remodel of Fire Station 62. The project, with an initial cost estimate of $4 million, will focus on updating the station’s bay area to meet current building codes.
Station 62 Remodel Key Points:
-
The board approved a construction manager agreement with Northern Builders.
-
The project has an initial estimated cost of $4 million.
-
The agreement terms are 5% of the project cost for management, plus 1% for insurance and the actual cost of work.
-
The remodel will bring the entire apparatus bay area up to current building codes.
The New Lenox Fire Protection District on Monday, July 21, 2025, took a major step toward modernizing one of its key facilities, approving a contract with a construction manager for a planned $4 million addition and remodel of Station 62.
The Board of Trustees voted unanimously to hire Northern Builders to oversee the project. According to the meeting minutes, the agreement stipulates that the construction manager’s fee will be 5% of the total project cost, with an additional 1% for insurance, plus the actual cost of the work performed.
The primary goal of the large-scale project is to update the station’s entire apparatus bay area to comply with current building codes, ensuring the facility meets modern safety and operational standards. District officials provided an initial cost estimate of $4 million for the capital improvement project.
Before the vote, the board confirmed that the district’s attorney, John Motylinski, had reviewed the contract with Northern Builders to ensure the terms were appropriate. Trustee Keith Popp made the motion to approve the agreement, which was seconded by Trustee Brian Fischer.
The motion passed with a 4-0 vote, with Trustees Skip Sauter, Cory Scanlan, Fischer, and Popp all in favor. Trustee Levey was absent. With the construction manager now officially in place, the district can move forward with the design and planning phases of the Station 62 overhaul.
Latest News Stories
WATCH: Trump says ‘dangerous’ Chicago next after addressing crime in D.C.
Gallego, others question Meta on policies for kids using AI
Commission enacted to aid young IL farmers facing challenges
Appeals court: Serious Chicago police disciplinary hearings must be public
WATCH: IL child welfare interns debate heats up; state financial audit released
Georgia ICE arrests up 367 percent from 2021, making for ‘safer streets, open jobs
Illinois quick hits: CUB challenges Ameren rate hike plan
Experts call for probe after Microsoft left out China ties in Pentagon security plan
FBI raids the home of John Bolton
Village Honors Life and Service of Late ESDA Deputy Director Bill Pitakei
Meeting Summary and Briefs: Lincoln-Way District 210 Board of Education for August 18, 2025
New Lenox Fire Board Denies Homeowner’s Request for Sprinkler System Variance