New Lenox Fire District Approves Contract for $4 Million Station 62 Remodel
New Lenox Fire Protection District Meeting | July 2025
Article Summary: The New Lenox Fire Protection District Board of Trustees has approved a contract with Northern Builders to manage the upcoming addition and remodel of Fire Station 62. The project, with an initial cost estimate of $4 million, will focus on updating the station’s bay area to meet current building codes.
Station 62 Remodel Key Points:
-
The board approved a construction manager agreement with Northern Builders.
-
The project has an initial estimated cost of $4 million.
-
The agreement terms are 5% of the project cost for management, plus 1% for insurance and the actual cost of work.
-
The remodel will bring the entire apparatus bay area up to current building codes.
The New Lenox Fire Protection District on Monday, July 21, 2025, took a major step toward modernizing one of its key facilities, approving a contract with a construction manager for a planned $4 million addition and remodel of Station 62.
The Board of Trustees voted unanimously to hire Northern Builders to oversee the project. According to the meeting minutes, the agreement stipulates that the construction manager’s fee will be 5% of the total project cost, with an additional 1% for insurance, plus the actual cost of the work performed.
The primary goal of the large-scale project is to update the station’s entire apparatus bay area to comply with current building codes, ensuring the facility meets modern safety and operational standards. District officials provided an initial cost estimate of $4 million for the capital improvement project.
Before the vote, the board confirmed that the district’s attorney, John Motylinski, had reviewed the contract with Northern Builders to ensure the terms were appropriate. Trustee Keith Popp made the motion to approve the agreement, which was seconded by Trustee Brian Fischer.
The motion passed with a 4-0 vote, with Trustees Skip Sauter, Cory Scanlan, Fischer, and Popp all in favor. Trustee Levey was absent. With the construction manager now officially in place, the district can move forward with the design and planning phases of the Station 62 overhaul.
Latest News Stories
Undersheriff Brian Conser Retires After 29 Years of Service
Officials warn against limits on loans for nursing students
FBI to scrap $5 billion move, Patel says
AGs say ‘As You Sow’ may violate antitrust laws with anti-fossil fuel alliance
Storm hits California over Christmas; flood watch continues
IL dyslexia screening takes effect Jan. 1, drawing reading instruction debate
Colorado Springs, Denver residents pay among lowest property taxes in U.S.
Illinois quick hits: Pope reacts to Pritzker bill signing
Study reveals top U.S. states for K-12 education
2025: More than 2.5 million removed, record number of violent offenders arrested
Trump to meet Zelensky in Florida Sunday
New Lenox Bans Truck Terminals in C-3 District, Lowers Development Fees