Will County’s “First-in-Nation” Veterans Center to House Workforce Services, Sparking Debate

Spread the love

ARTICLE SUMMARY: The new Will County Veteran’s Assistance & Support Center will also become the home for the county’s Workforce Services department, a move officials say will save approximately $250,000 in annual rent but which drew questions from board members about future expansion space for veteran needs.


Capital Improvements Committee Meeting Key Points:

  • Floors one and two of the 1300 Copperfield building in Joliet are being renovated for the Veteran’s Assistance Commission (VAC), more than doubling its current space to 35,000 square feet.

  • The third floor will be built out for Workforce Services, which will relocate from a rented facility.

  • Officials are developing a five-year plan for the fourth floor, with possibilities including emergency housing for homeless veterans or rental space for veteran-focused non-profits.

  • The entire project is progressing toward a late 2025 completion, though supply chain issues with air handling units present a potential delay.

JOLIET, IL – Will County’s ambitious plan to create a “first-in-the-nation” veterans support campus will include housing the county’s Workforce Services department, a move that sparked debate among Capital Improvements & IT Committee members Tuesday over long-term space for veteran programs.

During a facilities update, county staff confirmed that while the first two floors of the recently acquired building at 1300 Copperfield are dedicated to the Veteran’s Assistance Commission (VAC), the third floor is slated for Workforce Services.

County staff member Mike Mahoney explained the move will save the county approximately $250,000 per year by eliminating the need to rent a separate facility for the department.

The revelation prompted questions from Committee Member Julie Berkowicz, who voiced concern that allocating a floor to another department could limit the VAC’s ability to grow.

“My concern is about expenditures and costs to the county,” Berkowicz said. “Our veteran needs are expanding… Are we taking away the ability to expand those services in Copperfield?”

Mahoney countered that the project dramatically increases the VAC’s footprint from its current 12,000 square feet to 35,000 square feet. He assured the committee that the county is working closely with VAC leadership and planning for the future.

“The good news is your concerns are unwarranted,” Mahoney said. “We are doubling, tripling the space that VAC currently has and we meet with the VAC regularly… We’re working on about a five-year plan with the VAC for future space needs and what that fourth floor can entail.”

Potential uses for the top floor include emergency housing for homeless veterans, which would require a zoning change and 24/7 staffing, or creating space that veteran-focused non-profits could rent from the county.

The project, described as the first of its kind in the nation, creates a comprehensive campus by co-locating the expanded VAC services next to a federal VA clinic and the Hope Manor residential facility. Mahoney noted that federal, state, and local officials are in regular contact and excited about the project.

Berkowicz requested documentation of the County Board’s vote to approve the renovation for Workforce Services. Staff indicated the funding was part of the overall budget approval for the Copperfield building project passed last year and would provide the record.

Construction on the VAC and Workforce Services spaces is underway, with a total buildout cost expected to be under $3.5 million. The project has faced some supply chain delays for critical components like rooftop air handlers, which are now expected in late September. While officials are hopeful for a fall completion, the timeline may extend to the end of the year.

Today Jun 12
Mostly Sunny then Slight Chance Showers And Thunderstorms
87° 61°

Mostly Sunny then Slight Chance Showers And Thunderstorms

💨 5 to 15 mph 💧 17%

Leave a Comment





Latest News Stories

Meeting Briefs

Meeting Summary and Briefs: New Lenox Community Park District for August 2025

New Lenox Community Park District Meeting | August 2025 The New Lenox Community Park District Board of Commissioners reviewed major financial news and celebrated a record-breaking month for its golf...
Pavlov Media

Pavlov Media to Bring New Fiber Internet Option to New Lenox

Village of New Lenox Board of Trustees Meeting | September 22, 2025 Article Summary: The entrance to the Wintrust Crossroads Sports Complex is set to receive a major aesthetic upgrade...
Enbridge Energy

Will County to Pay Enbridge $82,000 to Relocate Pipeline Equipment for Exchange Street Improvements

Article Summary: Will County will reimburse Enbridge Energy for costs associated with relocating its pipeline facilities to make way for roadway improvements on Exchange Street in the Monee and Crete...
diamond shaped orange red reflector street sign that reads road

Laraway Road Widening Project in New Lenox and Frankfort Gets Additional $468,000 for Redesign

Article Summary: The Will County Board approved a supplemental agreement worth $468,374 for additional design and engineering work on the major Laraway Road expansion project. The funds are needed for...
solar panels photovoltaics in solar farm

“Federal Policy Uncertainty” Blamed for Delay of Peotone Solar Farm; County Grants Second Extension

Article Summary: The Will County Board has granted a second permit extension for a solar farm in Peotone Township after the developer, Trajectory Energy Partners, cited "ongoing uncertainty regarding federal...
solar panels photovoltaics in solar farm

Will County Grants Extensions to Five Solar Projects Sold to New Developers

Article Summary: The Will County Board approved first-time permit extensions for five commercial solar projects across Monee, Crete, and Joliet townships, all of which were recently sold to larger energy...
WCO 2025-09-27 at 9.04.10 AM

Will County Board Approves Controversial Drug Recovery Retreat in Crete Township

Article Summary: The Will County Board has approved a special use permit for The Second Story Foundation to operate a long-term residential recovery program for men on a 68-acre horse...
new-lenox-fire-district-stations.3

Winter Start Unlikely for $4 Million New Lenox Fire Station 62 Remodel

New Lenox Fire Protection District Meeting | August 2025 Article Summary: The planned $4 million remodel of New Lenox Fire Station 62 faces a potential delay, as officials indicated a...
LWSRA-Blue-Logo-transparent

New LWSRA Sensory Bus Hits the Road Thanks to $30,000 Donation

New Lenox Community Park District Meeting | August 2025 Article Summary: The Lincoln-Way Special Recreation Association's new Sensory Bus is officially in service and has been well-received at community events....
Joliet-Junior-college.-Graphic-Logo.4

Joliet Junior College Honors Seven Long-Serving Employees Upon Retirement

Joliet Junior College Board of Trustees Meeting | September 2025 Article SummaryThe Joliet Junior College Board of Trustees formally recognized seven long-serving employees who are retiring, including Dr. Robert "Bob"...
New-Lenox-School-122.3

New Lenox Parent Challenges Busing Fee, Cites Safety Concerns and Budget Surplus

Meeting Summary and Briefs: New Lenox School District 122 Meeting | August 2025 Article Summary: A New Lenox parent addressed the School District 122 board to protest a $350 busing...
Screenshot 2025-11-03 at 11.39.46 AM

New Lenox Demands Over $422,000 From Developer to Complete Public Improvements

Village of New Lenox Board of Trustees Meeting | September 22, 2025 Article Summary: The Village of New Lenox is taking formal action to secure funds for unfinished public infrastructure...
new-lenox-fire-district-stations.4

New Lenox Fire District Pays Off Final Loan, Secures $75,000 State Grant

New Lenox Fire Protection District Meeting | August 2025 Article Summary: The New Lenox Fire Protection District has achieved a significant financial milestone by making the final payment on its...
New-Lenox-Sharons-Bay-Park

Damaged Drain Tiles at Bristol Park Face $107,000 Repair Bill

New Lenox Community Park District Meeting | August 2025 Article Summary: A comprehensive survey of the drainage system at Bristol Park has revealed that all of the clay tiles are...
Screenshot 2025-11-03 at 11.31.47 AM

New Lenox and Homer Glen Renew 20-Year Boundary Agreement, Defining Future Growth

Village of New Lenox Board of Trustees Meeting | September 22, 2025 Article Summary: The New Lenox Village Board has approved a new 20-year intergovernmental boundary agreement with the Village...