Monee Approves Over $566,000 Payment for New Public Works Facility Nearing Completion
Article Summary:
The Monee Village Board approved a payment of $566,134.16 for the ongoing construction of its new Public Works building. Officials reported the project is on track for a mid-August occupancy following the recent installation of a long-delayed electrical panel.
Public Works Building Key Points:
-
Payment request #13 for $566,134.16 to Professional Building Services Inc. was unanimously approved.
-
The facility is nearing completion after a key electrical panel, which had been on back order, was installed this week.
-
Occupancy is anticipated by mid-August, with a grand opening to be scheduled at a later date.
MONEE — The Village of Monee’s new Public Works facility is nearing the finish line, with the Village Board approving another major payment for the project at its Wednesday meeting.
Trustees unanimously authorized pay request #13 in the amount of $566,134.16 to the project’s construction manager, Professional Building Services Inc. The payment covers work completed through July 10, including significant progress from contractors for concrete, masonry, general construction, and flooring.
Public Works Trustee Doug Horne provided a construction update, highlighting a critical milestone. “If you recall last time we met here, there was a discussion of a delayed electrical panel and it was on back order,” Horne said. “Well, I’m happy to report that that is being installed this week.”
With the panel in place, the factory startup of essential systems is scheduled for the week of July 28. A preliminary walkthrough for building staff is planned for the week of August 4.
“We’re hopeful to have occupancy of the building by mid-August,” Horne added. “The grand opening is yet to be scheduled. We’ll worry about that once it’s online.”
The payment request was reviewed and certified by the Farnsworth Group and village staff, who confirmed it met the project’s plans and specifications.
Latest News Stories
WATCH: Lawmakers spar over taxpayer-funded Trump investigation
Chicago splits pension payments in hopes of Improving cash flow
Adequate preparation missing for GenAI in higher ed
Following GOP criticism, Pritzker finds $481.6 million in budget reserves
Critics slam Illinois’ $36M park grants as political, wasteful
First arrests made following St. Paul church attack, ‘more to come’
Illinois Quick Hits: Chicago pays OT to potentially ineligible workers
50 Donors Sought for Community Blood Drive on Jan. 29
County Authorizes Condemnation to Advance Francis and Marley Road Improvements
Board Approves 2026-2027 School Calendar
Arizona Senate panel backs renaming highway loop after Kirk
Index shows top states that support education freedom