Will County’s Major Capital Projects Hit Key Milestones, VAC Buildout on “Aggressive Schedule”

Spread the love

Will County is making significant headway on several major capital improvement projects, with the new Veterans Assistance Commission (VAC) & Support Center in Joliet on an “aggressive schedule” for a November completion, Facilities Director Bill Fern reported Tuesday.

During an update to the Will County Board’s Capital Improvements & IT Committee, Fern detailed progress across multiple county-owned properties, highlighting the extensive work at the former Silver Cross Hospital building at 1300 Copperfield Avenue, which will house the VAC.

“This is probably the biggest news we have at this point in time,” Fern said.

The VAC buildout has seen the full replacement of the front lobby glass and the installation of an advanced security camera system that issues audible warnings to trespassers and can automatically contact the police. The building’s roof is 95% finished, and crews have begun work on the interior space.

“We’re looking at getting them in there by November,” Fern told the committee. “Very aggressive schedule.”

In response to questions from board members, Fern confirmed the building will likely have “shared occupancy” with other county entities, though a full space needs analysis is still underway to determine the final tenants.

Other key projects are also moving toward completion:

  • Land Use/Public Defender Renovations: Work at 58 E. Clinton Street is nearly finished. One floor’s renovation is complete, another is underway, and the final move-in and consolidation is expected by the end of August 2025.

  • Court Annex/State’s Attorney Renovations: Following a bid opening on June 4, construction on interior modifications at 57 N. Ottawa Street is set to begin on July 17, with an anticipated completion in the fall of 2025.

  • Will County Courthouse: The long-awaited replacement of exterior stone panels is expected within the next 30 days as the natural product is currently being manufactured. Fern noted that the large scaffolding currently in place for protection will be removed, and a swing stage will be used for the installation.

The committee also learned that the parking lot at the River Valley Justice Center has been fully restored, with new surfacing, striping, and signage installed by the county’s Division of Transportation, a move that saved “a considerable amount of money.”


Today Jun 9
Mostly Sunny then Showers And Thunderstorms Likely
88° 70°

Mostly Sunny then Showers And Thunderstorms Likely

💨 5 to 20 mph 💧 70%

Leave a Comment





Latest News Stories

Meeting Briefs

Meeting Summary and Briefs: New Lenox Community Park District for August 2025

New Lenox Community Park District Meeting | August 2025 The New Lenox Community Park District Board of Commissioners reviewed major financial news and celebrated a record-breaking month for its golf...
Pavlov Media

Pavlov Media to Bring New Fiber Internet Option to New Lenox

Village of New Lenox Board of Trustees Meeting | September 22, 2025 Article Summary: The entrance to the Wintrust Crossroads Sports Complex is set to receive a major aesthetic upgrade...
Enbridge Energy

Will County to Pay Enbridge $82,000 to Relocate Pipeline Equipment for Exchange Street Improvements

Article Summary: Will County will reimburse Enbridge Energy for costs associated with relocating its pipeline facilities to make way for roadway improvements on Exchange Street in the Monee and Crete...
diamond shaped orange red reflector street sign that reads road

Laraway Road Widening Project in New Lenox and Frankfort Gets Additional $468,000 for Redesign

Article Summary: The Will County Board approved a supplemental agreement worth $468,374 for additional design and engineering work on the major Laraway Road expansion project. The funds are needed for...
solar panels photovoltaics in solar farm

“Federal Policy Uncertainty” Blamed for Delay of Peotone Solar Farm; County Grants Second Extension

Article Summary: The Will County Board has granted a second permit extension for a solar farm in Peotone Township after the developer, Trajectory Energy Partners, cited "ongoing uncertainty regarding federal...
solar panels photovoltaics in solar farm

Will County Grants Extensions to Five Solar Projects Sold to New Developers

Article Summary: The Will County Board approved first-time permit extensions for five commercial solar projects across Monee, Crete, and Joliet townships, all of which were recently sold to larger energy...
WCO 2025-09-27 at 9.04.10 AM

Will County Board Approves Controversial Drug Recovery Retreat in Crete Township

Article Summary: The Will County Board has approved a special use permit for The Second Story Foundation to operate a long-term residential recovery program for men on a 68-acre horse...
new-lenox-fire-district-stations.3

Winter Start Unlikely for $4 Million New Lenox Fire Station 62 Remodel

New Lenox Fire Protection District Meeting | August 2025 Article Summary: The planned $4 million remodel of New Lenox Fire Station 62 faces a potential delay, as officials indicated a...
LWSRA-Blue-Logo-transparent

New LWSRA Sensory Bus Hits the Road Thanks to $30,000 Donation

New Lenox Community Park District Meeting | August 2025 Article Summary: The Lincoln-Way Special Recreation Association's new Sensory Bus is officially in service and has been well-received at community events....
Joliet-Junior-college.-Graphic-Logo.4

Joliet Junior College Honors Seven Long-Serving Employees Upon Retirement

Joliet Junior College Board of Trustees Meeting | September 2025 Article SummaryThe Joliet Junior College Board of Trustees formally recognized seven long-serving employees who are retiring, including Dr. Robert "Bob"...
New-Lenox-School-122.3

New Lenox Parent Challenges Busing Fee, Cites Safety Concerns and Budget Surplus

Meeting Summary and Briefs: New Lenox School District 122 Meeting | August 2025 Article Summary: A New Lenox parent addressed the School District 122 board to protest a $350 busing...
Screenshot 2025-11-03 at 11.39.46 AM

New Lenox Demands Over $422,000 From Developer to Complete Public Improvements

Village of New Lenox Board of Trustees Meeting | September 22, 2025 Article Summary: The Village of New Lenox is taking formal action to secure funds for unfinished public infrastructure...
new-lenox-fire-district-stations.4

New Lenox Fire District Pays Off Final Loan, Secures $75,000 State Grant

New Lenox Fire Protection District Meeting | August 2025 Article Summary: The New Lenox Fire Protection District has achieved a significant financial milestone by making the final payment on its...
New-Lenox-Sharons-Bay-Park

Damaged Drain Tiles at Bristol Park Face $107,000 Repair Bill

New Lenox Community Park District Meeting | August 2025 Article Summary: A comprehensive survey of the drainage system at Bristol Park has revealed that all of the clay tiles are...
Screenshot 2025-11-03 at 11.31.47 AM

New Lenox and Homer Glen Renew 20-Year Boundary Agreement, Defining Future Growth

Village of New Lenox Board of Trustees Meeting | September 22, 2025 Article Summary: The New Lenox Village Board has approved a new 20-year intergovernmental boundary agreement with the Village...