Major Park District Projects Advance as Hunter Prairie Park Gets Green Light
Work on the Frankfort Square Park District’s three major capital projects is hitting key milestones, with the long-awaited redevelopment of Hunter Prairie Park now officially underway.
Executive Director Audrey Marcquenski announced at the June 12 board meeting that Will County granted the permit for the park’s redevelopment on June 9. The contractor, Innovation Landscaping, is mobilizing at the site, and a second erosion inspection is scheduled for June 16.
During the meeting, Treasurer Frank Florentine inquired about the scope of the construction fencing. Marcquenski confirmed the fencing is necessary to keep residents safe during construction and that all proper safety steps are being taken. Commissioner Phil Cherry asked if the grant funding for the project had an expiration date. Marcquenski said that if necessary, the district could request an extension from the Illinois Department of Natural Resources (IDNR).
Meanwhile, the new dance studios at The Square are now complete and have been approved for occupancy by the Frankfort Fire Protection District. Marcquenski commended Jeff Graefen and his Graefen Development construction crew for their quality work and cleanliness, noting the project was completed with no disruption to existing park district programming.
Work has also begun on the new practice area at Square Links Golf Course. The contractor, Hollembeak Construction, is trenching for drain tile and irrigation, with that work set to begin June 16. Marcquenski noted the contractor is a family-owned business with expertise in shoreline restoration and golf course construction.
Latest News Stories
Meeting Summary and Briefs: New Lenox Community Park District for August 2025
Pavlov Media to Bring New Fiber Internet Option to New Lenox
Will County to Pay Enbridge $82,000 to Relocate Pipeline Equipment for Exchange Street Improvements
Laraway Road Widening Project in New Lenox and Frankfort Gets Additional $468,000 for Redesign
“Federal Policy Uncertainty” Blamed for Delay of Peotone Solar Farm; County Grants Second Extension
Will County Grants Extensions to Five Solar Projects Sold to New Developers
Will County Board Approves Controversial Drug Recovery Retreat in Crete Township
Winter Start Unlikely for $4 Million New Lenox Fire Station 62 Remodel
New LWSRA Sensory Bus Hits the Road Thanks to $30,000 Donation
Joliet Junior College Honors Seven Long-Serving Employees Upon Retirement
New Lenox Parent Challenges Busing Fee, Cites Safety Concerns and Budget Surplus
New Lenox Demands Over $422,000 From Developer to Complete Public Improvements