Will County’s facilities team has completed several major projects while advancing others throughout the county, officials reported during a Capital Improvements & IT Committee meeting Monday.

The Old Courthouse Plaza concrete replacement project at 14 W. Jefferson has been finished, with new picnic benches installed and the area fully restored with handicap-accessible ramps meeting current ADA standards, according to Facilities Director Bill Fern.

“The plaza is completely usable again, safe level, all new concrete, all handicap ramps all been replaced,” Fern told committee members during his monthly facilities update.

The county has also completed parking lot resurfacing at both the Community Health Center and River Valley Juvenile Detention Center. The River Valley project addressed serious deterioration issues and brought handicap ramps up to current ADA compliance standards after the original construction was determined to be too steep by today’s requirements.

“That parking lot was in serious need of resurfacing,” Fern said. “The handicap ramps, the ADA accessible areas when they built it were too steep to today’s standards, so now they are all compliant.”

Work continues on several other major projects across county properties. The Court Annex/State’s Attorney Level 2 renovations at 57 N. Ottawa are scheduled to begin construction July 10 following bid openings set for June 4. The project, which involves combining unused courtrooms on the second and third floors to create more usable space, is expected to be completed by fall 2025.

Similarly, Land Use/Public Defender renovations at 58 E. Clinton are progressing with Level 3 complete and Level 4 work beginning June 16. That project is also slated for completion in August.

The Veterans Assistance Commission buildout at 1300 Copperfield has reached several milestones, with roof replacement 95% complete and both glass replacement and interior renovations set to begin June 9. The project involves UV-coated, double-pane glass replacement and is expected to wrap up in fall 2025.

Committee Chair Mica Freeman noted the county is expecting facility assessment reports by month’s end that will merge facility condition evaluations with space needs analysis. The comprehensive assessment covers 75% of county-owned properties, with the largest facilities – Adult Detention Facility and River Valley – nearing completion of their evaluations.

Fern reported his team handled over 760 work orders in May, completing them with 98% on-time performance at an average cost of $19.75 per work order. The facilities team logged more than 800 hours of labor during the month.

“The team is really moving,” Fern said, highlighting the department’s productivity while maintaining zero workplace injuries – a safety record Committee member Herbert Brooks Jr. praised as worthy of celebration.

The committee also addressed ongoing courthouse issues, with scaffolding removal underway as stone replacement work continues. Water infiltration behind limestone panels caused damage when freezing temperatures expanded the moisture, pushing stones outward. Sixteen new quarried limestone pieces are being manufactured for replacement, with installation planned using swing stages rather than scaffolding.

A facilities report from material specialists examining the courthouse damage is expected by the end of next week, providing definitive analysis of the stone failure and remediation efforts.

The next committee meeting is scheduled for July 1.

Events

No events

Leave a Comment





Latest News Stories

Screenshot 2025-10-10 at 11.36.42 AM

Will County Eyes Major Overhaul to Consolidate Scattered Government Offices

Will County Capital Improvements & IT Committee Meeting October 7, 2025 Article Summary: Will County officials are formally debating a new facilities master plan to address aging buildings and dozens...
Screenshot 2025-10-10 at 11.20.27 AM

Sheriff’s Office Reports Crime Down 10%, Cites Body Cam Footage as Main Challenge of Safety Act

Will County Public Health & Safety Committee Meeting October 2, 2025 Article Summary: The Will County Sheriff's Office reported a nearly 10% overall drop in crime compared to the same...
Screenshot 2025-10-10 at 11.52.24 AM

Will County Considers Moving Land Use Public Hearings Away from Full Board Meetings

Will County Executive Committee Meeting October 9, 2025 Article Summary: A proposal to move the final public hearing for zoning and land use cases from the full Will County Board...
WCO 2025-09-27 at 9.04.36 AM

Meeting Summary and Briefs: Will County Board for September 18, 2025

The Will County Board navigated a contentious meeting on September 18, 2025, marked by narrow votes on two highly debated land use issues in Crete and Homer Glen. The board...
Meeting Briefs

Meeting Summary and Briefs: Lincoln-Way Community High School District 210 Board of Education for September 18, 2025

The Lincoln-Way Community High School District 210 Board of Education on Thursday, September 18, 2025, formally adopted a $172.7 million budget for the 2025-2026 school year. The budget includes a...
lincoln way school district 210 logo.1

Lincoln-Way 210 to Launch District Literacy Plan, Expands Community Partnerships

Article Summary: As part of its strategic plan, Lincoln-Way High School District 210 is developing a comprehensive literacy plan to embed critical thinking skills across the curriculum. The district is also...
WCO 2025-09-27 at 9.05.04 AM

County Board Abates Over $25 Million in Property Taxes for Bond Payments

Article Summary: Will County property taxpayers will be spared over $25 million in taxes for the 2026 payment year after the County Board voted to abate taxes for six separate...
Screenshot

Lincoln-Way 210 Prepares for “Retirement Wave” with Focus on Recruitment

Article Summary: Lincoln-Way High School District 210 is bracing for a significant number of retirements, with 47 teachers expected to leave over the next four years, representing nearly a quarter of...
Meeting-Briefs

Meeting Summary and Briefs: Village of New Lenox Board of Trustees for September 22, 2025

Village of New Lenox Board of Trustees Meeting | September 22, 2025 The New Lenox Village Board, meeting on September 22, 2025, with Trustee Keith Madsen presiding in the mayor's...
lincoln way school district 210 logo.2

Lincoln-Way Board Weighs Community Solar Program Promising $155,000 in Annual Savings

Article Summary: The Lincoln-Way District 210 board is considering a 20-year agreement to participate in a state-sponsored community solar program that could save the district an estimated $155,000 annually on electricity...
Meeting Briefs

Meeting Summary and Briefs: New Lenox Fire Protection District for August 2025

New Lenox Fire Protection District Meeting | August 2025 The New Lenox Fire Protection District Board of Trustees celebrated strong fiscal health and discussed project timelines at its meeting on...
Meeting Briefs

Meeting Summary and Briefs: New Lenox School District 122 for August 2025

Meeting Summary and Briefs: New Lenox School District 122 Meeting | August 2025 The New Lenox School District 122 Board of Education took a major step toward modernizing another of...
WCO 2025-09-27 at 9.04.56 AM

Will County Reverses Zoning on Peotone Farmland to Facilitate 10-Acre Sale

Article Summary: The Will County Board unanimously approved a request to rezone a 10.08-acre portion of a property in Will Township back to agricultural use, reversing a 2023 zoning change....
Meeting Briefs

Meeting Summary and Briefs: Joliet Junior College Board of Trustees for September 10, 2025

Joliet Junior College Board of Trustees Meeting | September 2025 The Joliet Junior College (JJC) Board of Trustees approved a landmark agreement with the City of Joliet to explore a...
Screenshot

Lincoln-Way 210 Board Approves $172.7 Million Budget with Planned Deficit for Bus Purchases

Article Summary: The Lincoln-Way Community High School District 210 Board of Education approved the Fiscal Year 2026 budget, which includes a planned operating deficit of $814,000 to accommodate the purchase of...