Will County completes major projects while others move forward

Will County’s facilities team has completed several major projects while advancing others throughout the county, officials reported during a Capital Improvements & IT Committee meeting Monday.

The Old Courthouse Plaza concrete replacement project at 14 W. Jefferson has been finished, with new picnic benches installed and the area fully restored with handicap-accessible ramps meeting current ADA standards, according to Facilities Director Bill Fern.

“The plaza is completely usable again, safe level, all new concrete, all handicap ramps all been replaced,” Fern told committee members during his monthly facilities update.

The county has also completed parking lot resurfacing at both the Community Health Center and River Valley Juvenile Detention Center. The River Valley project addressed serious deterioration issues and brought handicap ramps up to current ADA compliance standards after the original construction was determined to be too steep by today’s requirements.

“That parking lot was in serious need of resurfacing,” Fern said. “The handicap ramps, the ADA accessible areas when they built it were too steep to today’s standards, so now they are all compliant.”

Work continues on several other major projects across county properties. The Court Annex/State’s Attorney Level 2 renovations at 57 N. Ottawa are scheduled to begin construction July 10 following bid openings set for June 4. The project, which involves combining unused courtrooms on the second and third floors to create more usable space, is expected to be completed by fall 2025.

Similarly, Land Use/Public Defender renovations at 58 E. Clinton are progressing with Level 3 complete and Level 4 work beginning June 16. That project is also slated for completion in August.

The Veterans Assistance Commission buildout at 1300 Copperfield has reached several milestones, with roof replacement 95% complete and both glass replacement and interior renovations set to begin June 9. The project involves UV-coated, double-pane glass replacement and is expected to wrap up in fall 2025.

Committee Chair Mica Freeman noted the county is expecting facility assessment reports by month’s end that will merge facility condition evaluations with space needs analysis. The comprehensive assessment covers 75% of county-owned properties, with the largest facilities – Adult Detention Facility and River Valley – nearing completion of their evaluations.

Fern reported his team handled over 760 work orders in May, completing them with 98% on-time performance at an average cost of $19.75 per work order. The facilities team logged more than 800 hours of labor during the month.

“The team is really moving,” Fern said, highlighting the department’s productivity while maintaining zero workplace injuries – a safety record Committee member Herbert Brooks Jr. praised as worthy of celebration.

The committee also addressed ongoing courthouse issues, with scaffolding removal underway as stone replacement work continues. Water infiltration behind limestone panels caused damage when freezing temperatures expanded the moisture, pushing stones outward. Sixteen new quarried limestone pieces are being manufactured for replacement, with installation planned using swing stages rather than scaffolding.

A facilities report from material specialists examining the courthouse damage is expected by the end of next week, providing definitive analysis of the stone failure and remediation efforts.

The next committee meeting is scheduled for July 1.

Events

No events

Leave a Comment





Latest News Stories

will-county-board.2

Major Grade Separation Projects Advance with Engineering Contracts

The committee approved two significant engineering agreements for major railroad overpass projects totaling over $4 million. TranSystems Corporation received a $4,003,256 contract for construction engineering services on the Lorenzo Road...
County-Board-Room

County Authorizes Condemnation for Francis Road Project

The committee authorized the State's Attorney's Office to proceed with condemnation cases for right-of-way acquisition needed for Francis Road improvements between Gougar Road and Interstate 80. Eight property parcels are...
will-county-board

Solar Farm Access Approved for Manhattan-Arsenal Road

The committee granted access approval for a solar farm development on Manhattan-Arsenal Road approximately 1,000 feet east of Cherry Hill Road. The MCH Solar 1 project, developed by Soltage LLC,...
will-county-board.3

Will County Finance Committee Meeting Briefs

Budget Transfers Approved: The Finance Committee approved transferring $18,643 within the Supervisor of Assessments budget to move funds from software licensing to computer hardware purchases. Animal Protection Services Funding: Committee...
will-county-board.2

Public Works Committee Briefs

Major Projects Update: Construction continues on several major projects including the 80th Avenue expressway overpass, Laraway Road widening near Cedar Road, and Bell Road improvements. The Bell Road project at...
will-county-board

Capital Improvements & IT Committee Briefs

Bed donation program: Will County donated old beds from Sunny Hill Nursing Home to Joliet Junior College and Project Cure after the nursing home received all new beds for residents....
Frankfort-Village-Board-Meeting-Graphic

Frankfort Board Approves New Wendy’s on Route 30 With Numerous Modifications

A new Wendy's restaurant is set to be built at the northwest corner of U.S. Route 30 and Frankfort Square Road after the Frankfort Village Board unanimously approved the project...
Frankfort-Village-Board-Meeting-Graphic

Historic Downtown Frankfort Property Granted Deck and Patio Variances

The owners of a historic mixed-use building in downtown Frankfort have received approval for six zoning variances to construct a new paver patio and a second-floor rear deck. The Frankfort...
Frankfort-Village-Board-Meeting-Graphic

Frankfort Approves $1.3 Million in Bills, Including Annual Insurance Payment

The Frankfort Village Board authorized over $1.3 million in payments at its meeting Monday, with nearly half of the total amount covering the village's annual insurance premiums. Trustees unanimously approved...
Meeting-Briefs

Meeting Briefs: Frankfort Village Board for June 2, 2025

Wendy's Project Approved with Multiple Variances: The Village Board gave final approval for a new Wendy's restaurant at U.S. Route 30 and Frankfort Square Road. The project required a major change...
frankfort-park-district.1

Frankfort Park Board Holds Closed-Door Talks on Five Oaks HOA Dispute

The Frankfort Park District Board of Commissioners entered into a closed executive session on Tuesday, May 27, to discuss pending litigation concerning the Five Oaks Park parcel, signaling a deepening...
Frankfort-Township-Logo-Graphic

Frankfort Township Approves Employee Raises, Details Major Infrastructure and Service Projects

Frankfort Township employees will receive a 2.5% cost-of-living pay increase after the Board of Trustees unanimously approved the adjustment at its Monday, May 19 meeting. The move came as Supervisor...
Frankfort-Township-Logo-Graphic

New High-End Bar ‘Ace & Vine’ Gets Green Light from Township Board

A new bar focused on high-end liquor and an extensive wine collection is one step closer to opening in Frankfort Township after the Board of Trustees voted to recommend a...
Frankfort-Township-Logo-Graphic

Golf Carts Not Permitted on Township Roads, Supervisor Clarifies

Residents hoping to drive golf carts on roads in unincorporated Frankfort Township are out of luck, as the practice is illegal under state law, Supervisor Nick George clarified at the...
Frankfort-Township-Logo-Graphic

Meeting Briefs: Frankfort Township Board for May 19, 2025

The Frankfort Township Board approved a 2.5% cost-of-living raise for its employees and discussed several major projects at its meeting on Monday, May 19. Supervisor Nick George announced that the...