Village Board Approves Industrial Rezoning on Gougar Road Over Resident Protests, But Freezes Construction for Years

Spread the love

New Lenox Village Board of Trustees Meeting | April 27, 2026

Article Summary:
Following intense pushback from neighboring residents, the New Lenox Village Board approved a development agreement and rezoning for a Northern Builders industrial project south of Laraway Road. However, to mitigate traffic concerns, the Village mandated a strict freeze preventing the developer from starting construction or receiving occupancy until major county road and overpass improvements are completed.

Gougar Road Industrial Development Key Points:

  • Zoning Approval: The Board passed ordinances authorizing a Development Agreement and rezoning the property at the southwest corner of Laraway Road and Gougar Road (extended) to I-1 Limited Industrial.

  • Resident Backlash: Multiple residents from nearby subdivisions like Jacob’s Field and Country View argued the warehouses will bring dangerous truck traffic near schools and destroy the residential character of the area.

  • Construction Freeze: Northern Builders cannot obtain a building permit until the county begins widening Gougar Road and constructing the CN railroad overpass, or a period of three years expires.

  • Occupancy Block: The developer cannot receive a Certificate of Occupancy until the road improvements are completely finished, or four years expire.

The New Lenox Village Board on Monday, April 27, 2026, voted to approve the rezoning of agricultural land for industrial warehouse use along Gougar Road, balancing developer rights with resident fury by attaching strict, multi-year road construction contingencies to the project.

The Board passed an Ordinance Authorizing a Development Agreement with Cherry Hill Laraway LLC (Northern Builders) and a subsequent Ordinance Rezoning the property at the southwest corner of Laraway Road and the future Gougar Road extension.

The approvals followed a second round of intense public comment from residents representing nearby subdivisions, including Jacob’s Field and Country View. Residents fiercely objected to the prospect of heavy semi-truck traffic bleeding into residential zones.

“I don’t understand how more trucks on our roads near a high school, near grade schools… makes that statement true when this gets built,” said resident Mike Gian Paulo. “I don’t understand how this benefits New Lenox… I see how it benefits certain corporations.”

Resident Dennis McLaclin argued the development was encroaching on established neighborhoods that have been there since the 1970s.

“No one wanted that there. No one wants these warehouses there, and they’re being shoved on them,” McLaclin told the Board. “There’s plenty of open spots for these warehouses. They got hundreds of available acres in that park.”

In response to the public outcry, the Village forced Northern Builders to accept a highly unusual timeline restriction. Community Development Director Robin Ellis explained that the developer must dedicate the right-of-way along their entire frontage and construct a landscaped berm. Crucially, they are legally barred from receiving a building permit until construction physically begins on the county’s widening of Gougar Road and the new CN railroad overpass, or until three years have passed. Furthermore, the Village will not issue a Certificate of Occupancy until those road improvements are entirely complete, or four years have passed.

Matthew Garci, representing Northern Builders, confirmed the developer had agreed to the terms and was actively working with the Illinois Department of Transportation (IDOT) and Will County to dedicate the necessary land for the overpass.

“Based on our first reading of this, to be responsive and to work appropriately with staff, we resided to the idea that okay, we’re going to carry this… we’re going to sit on it for three years,” Garci said. “We have that carry cost for that period of time, which is fine.”

Mayor Tim Baldermann defended the Board’s decision, noting that the Village has kept its long-standing promise to prevent industrial development from crossing east of Gougar Road. He pointed out that the Village previously relocated the new Water Resource Recovery Facility away from residential areas to accommodate public demand, leaving this specific parcel open for commercial or industrial growth.

“Our commitment was to keep everything west of Gougar, which this is, and to say, ‘Okay, they’re ready to go now. No, you need to wait,'” Baldermann said. “That’s very unusual for us to say that… But we’re doing everything we can to accommodate the residents and the business owner.”

Both the Development Agreement and the rezoning ordinances passed on 6-0 roll call votes.

Leave a Comment





Latest News Stories

Jack Daniel’s maker faces foreign takeover push

Jack Daniel’s maker faces foreign takeover push

By Tom JoyceThe Center Square The company that makes one of America’s most popular whiskey brands is receiving interest from both foreign and domestic buyers. Louisville-based Brown-Forman, which makes Jack...
Pritzker pushes housing plan described as 'all stick,' no carrot

Pritzker pushes housing plan described as ‘all stick,’ no carrot

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – Gov. J.B. Pritzker is pushing to prevent local communities from restricting housing development, but local leaders say...
Alleged attacker charged with attempted assassination of Trump

Alleged attacker charged with attempted assassination of Trump

By Andrew RiceThe Center Square The man accused of storming the White House Correspondents' Associations Dinner has been charged with the attempted assassination of President Donald Trump. Cole Tomas Allen...
Republican lawmakers say shooting proves need for Trump ballroom

Republican lawmakers say shooting proves need for Trump ballroom

By Thérèse BoudreauxThe Center Square In light of the Saturday shooting at the White House Correspondents’ Association dinner, congressional Republicans are calling for an end to the Department of Homeland...
White House calls for DHS funding after correspondents incident

White House calls for DHS funding after correspondents incident

By Andrew RiceThe Center Square The White House on Monday called on Congress to fund the U.S. Department of Homeland Security after shots were fired at the White House Correspondents'...
Report: $186 billion in federal payment errors likely an undercount

Report: $186 billion in federal payment errors likely an undercount

By Brett RowlandThe Center Square Federal agencies made an estimated $186 billion in improper payments in fiscal year 2025, a $24 billion increase from the prior year, according to a...
Convenience store advocate: Swipe fee ruling is 'one step' in the process

Convenience store advocate: Swipe fee ruling is ‘one step’ in the process

By Jim TalamontiThe Center Square *The Center Square) – The federal government has moved to partially block an Illinois law banning electronic processing fees on the tax and tip portions...
Report: Sharp ideological divide in Minnesota congressional delegation

Report: Sharp ideological divide in Minnesota congressional delegation

By Elyse ApelThe Center Square A new report analyzing congressional voting records shows a clear ideological divide between Minnesota’s Republican and Democratic delegations. In its idealogical rankings, the Institute for...
White House correspondents' dinner shooter faces formal charges

White House correspondents’ dinner shooter faces formal charges

By Thérèse BoudreauxThe Center Square The California man accused of charging security and shooting a Secret Service officer at the White House Correspondents' Association dinner Saturday night will appear Monday...
Deferred maintenance blamed in I-64 bridge hole

Deferred maintenance blamed in I-64 bridge hole

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – State transportation officials say repairs are underway after a large hole developed on an Interstate 64...
Supreme Court strikes down Texas redistricting lawsuit, upholds new maps

Supreme Court strikes down Texas redistricting lawsuit, upholds new maps

By Andrew RiceThe Center Square The U.S. Supreme Court on Monday struck down a challenge to Texas' new congressional maps. The court reversed Abbott v. LULAC, a case that sought...
Supreme Court to hear migrant farm worker case

Supreme Court to hear migrant farm worker case

By Andrew RiceThe Center Square The U.S. Supreme Court will hear a case over the constitutional authority of federal agencies to handle migrant farmworker disputes. The case, Department of Labor...
Illinois quick hits: Convicted felon suspected of shooting two officers; Chicago Mayor orders up to $900,000 for additional peacekeepers; Belleville man faces attempted murder charge

Illinois quick hits: Convicted felon suspected of shooting two officers; Chicago Mayor orders up to $900,000 for additional peacekeepers; Belleville man faces attempted murder charge

By Jim Talamonti | The Center SquareThe Center Square Convicted felony suspected of shooting two officers One Chicago police officer is dead and another was critically injured after a man...
Screenshot 2026-04-25 at 8.34.35 AM

Lincoln-Way D210 Approves $483,000 Agreement with Illinois Bone and Joint Institute, Adds Seventh Athletic Trainer

Lincoln-Way Community High School District 210 Meeting | April 16, 2026 Article Summary: The Board of Education approved a new three-year, $483,000 contract with the Illinois Bone and Joint Institute...
New-Lenox-School-122.6

New Lenox 122 Board Approves Three-Year Contract Extension for Support Staff

New Lenox School District 122 Meeting | March 19, 2026 Article Summary: The Board of Education secured long-term labor stability by approving a three-year contract extension for the New Lenox Professional...